4449 W LOCKWOOD AVE 90029
Certificate Information: 4449 W LOCKWOOD AVE 90029
- Application / Permit
- 19016-10000-07546
- Plan Check / Job No.
- B19LA05403
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL 3 (N) SCCS AND ONE (N) OMF.
- Permit Issued
- Issued on 6/24/2020
- Issuing Office
- Current Status
- CofC Issued on 4/20/2021
Permit Application Status History
| Submitted | 3/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2019 | JAIME OROZCO |
| Corrections Issued | 4/18/2019 | JAIME OROZCO |
| Quality Review Completed | 4/18/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 4/19/2019 | APPLICANT |
| Applicant returned to address corrections | 8/20/2019 | VARAND SARKISIAN |
| Plan Check Approved | 8/27/2019 | VARAND SARKISIAN |
| Issued | 6/24/2020 | APPLICANT |
| OK for CofC | 4/13/2021 | JONATHAN QUACH |
| CofC Issued | 4/20/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 4/15/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Top World Engineering & Construction Co; Lic. No.: 621957-B | 6101 OWENSMOUTH AVE STE 154 WOODLAND HILLS, CA 91364 |
| Engineer | Farmand,, Anthony E; Lic. No.: C62595 | 2372 MORSE AVE STE 137 IRVINE, CA 92614 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/14/2020 | Approved | MARK FERRARI |
| Pre-Inspection | 9/8/2020 | Corrections Issued | MARK FERRARI |
| Deputy Steel/Welding | 10/22/2020 | Conditional Approval | FRED WOHLFARTH |
| Deputy Drilled-In Anchors | 11/5/2020 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 11/6/2020 | Not Ready for Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 11/6/2020 | Not Ready for Inspection | MARK FERRARI |
| Reinforced Concrete Frame | 11/6/2020 | Not Ready for Inspection | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 11/10/2020 | Partial Approval | MARK FERRARI |
| Special/Order Compliance | 11/10/2020 | Not Ready for Inspection | MARK FERRARI |
| Structural Steel Frame | 11/25/2020 | Not Ready for Inspection | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2020 | Partial Approval | MARK FERRARI |
| Wood Frame | 12/1/2020 | Corrections Issued | MARK FERRARI |
| Structural Steel Frame | 12/3/2020 | Approved | MARK FERRARI |
| Wood Frame | 12/3/2020 | Corrections Issued | MARK FERRARI |
| Interior/Exterior Lathing | 12/21/2020 | Corrections Issued | JONATHAN QUACH |
| Final | 2/5/2021 | Conditional Approval | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 2/5/2021 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 2/5/2021 | Approved | JONATHAN QUACH |
| Final | 4/13/2021 | OK for CofC | JONATHAN QUACH |