743 S HARVARD BLVD 90005
Certificate Information: 743 S HARVARD BLVD 90005
- Application / Permit
- 19016-10000-07439
- Plan Check / Job No.
- B19LA05327
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft Story Retrofit as per LABC Ch. 93. 3 SCCS.
- Permit Issued
- Issued on 4/11/2022
- Issuing Office
- Current Status
- CofC Issued on 11/3/2022
Permit Application Status History
| Submitted | 3/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2019 | DANIEL SANJUAN |
| Corrections Issued | 4/26/2019 | DANIEL SANJUAN |
| Quality Review Completed | 4/30/2019 | SAI KHUM |
| Building Plans Picked Up | 5/6/2019 | APPLICANT |
| Plan Check Approved | 5/30/2019 | DANIEL SANJUAN |
| Issued | 4/11/2022 | APPLICANT |
| OK for CofC | 10/26/2022 | DARRYL ARNOLD |
| CofC Issued | 11/3/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 5/30/2019 | JIM URQUHART |
| Housing rent stabilization | Cleared | 4/4/2022 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Cha Kyungmin; Lic. No.: 1018067-B | 917 S NEW HAMPSHIRE AVENUE 103 LOS ANGELES, CA 90006 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/26/2022 | Conditional Approval | DARRYL ARNOLD |
| Pre-Inspection | 7/26/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/9/2022 | Approved | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 8/12/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 8/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 8/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 9/26/2022 | Approved | DARRYL ARNOLD |
| Final | 10/26/2022 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 10/26/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 10/26/2022 | Approved | DARRYL ARNOLD |