1170 W 21ST ST 90731

Certificate Information: 1170 W 21ST ST 90731

Application / Permit
19016-10000-07423
Plan Check / Job No.
B19LA05319
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT A PORTION OF EXISTING DETACHED GARAGE (17'-6" X 22'-0") INTO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 5/27/2020
Issuing Office
Metro
Current Status
CofO Issued on 6/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2019 APPLICANT
Assigned to Plan Check Engineer 3/15/2019 MICHAEL LOPEZ
Corrections Issued 3/15/2019 MICHAEL LOPEZ
Plan Check Approved 4/8/2019 SINA KHOSRAVI
Issued 5/27/2020 LADBS
Building Plans Picked Up 6/1/2020 APPLICANT
CofO in Progress 6/21/2025 MICHAEL PELHAM
Permit Finaled 6/23/2025 RICHARD STEINBACH
CofO Issued 6/23/2025 RICHARD STEINBACH
Permit Finaled 6/23/2025 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/28/2019 JONATHAN HOM
Address approval Cleared 4/8/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 4/8/2019 ERIK BEASLEY
Sewer availability Cleared 4/8/2019 ERIK BEASLEY

Contact Information

Contractor Hilltop Design-Build Inc; Lic. No.: 969696-B 1441 W 7TH STREET 2ND FLOOR      SAN PEDRO, CA 90732

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 6/12/2020 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 7/8/2020 Approved JOHN KLARIN
ELECTRICAL-Rough 7/8/2020 Approved JOHN KLARIN
Green Building Rough 7/8/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 7/8/2020 Approved JOHN KLARIN
PLUMBING-Rough 7/8/2020 Approved JOHN KLARIN
Insulation 7/10/2020 Approved JOHN KLARIN
Shower Pan 7/10/2020 Approved JOHN KLARIN
Drywall Nailing 7/16/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 7/16/2020 Approved JOHN KLARIN
Final 8/28/2020 Corrections Issued JOHN KLARIN
Green Building Final 8/28/2020 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 8/28/2020 SGSOV Approved JOHN KLARIN
Smoke Detectors 8/28/2020 Approved JOHN KLARIN
Final 9/23/2020 Not Ready for Inspection JOHN KLARIN
Final 10/2/2020 Corrections Issued JOHN KLARIN
Special/Order Compliance 3/25/2021 Corrections Issued JOHN KLARIN
Special/Order Compliance 10/28/2024 No Access for Inspection JOSEPH MCGARRY
Final 6/21/2025 OK to Issue CofO MICHAEL PELHAM