642 N GRAND AVE 90012
Certificate Information: 642 N GRAND AVE 90012
- Application / Permit
- 19016-10000-07350
- Plan Check / Job No.
- B19LA05259
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMN
- Permit Issued
- Issued on 3/12/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 8/18/2020
Permit Application Status History
| Submitted | 3/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2019 | HANS SANTIAGO |
| Corrections Issued | 4/15/2019 | HANS SANTIAGO |
| Quality Review Completed | 4/16/2019 | SAI KHUM |
| Building Plans Picked Up | 4/23/2019 | APPLICANT |
| Plan Check Approved | 8/20/2019 | ANDREW SANTIAGO |
| Issued | 3/12/2020 | LADBS |
| OK for CofC | 8/10/2020 | VAHE KELEDJIAN |
| CofC Issued | 8/18/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 6/18/2019 | JIM URQUHART |
| Housing rent stabilization | Cleared | 3/9/2020 | CHARLES GARCIA |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-A | 15643 SHERMAN WAY STE 220 VAN NUYS, CA 91406 |
| Engineer | Au,, Chi-Ming; Lic. No.: C44491 | 8857 ARDENDALE AVE SAN GABRIEL, CA 91775 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/2/2020 | Approved | MARK FERRARI |
| Deputy Steel/Welding | 4/13/2020 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 4/16/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 4/17/2020 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 4/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 4/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 4/20/2020 | Conditional Approval | MARK FERRARI |
| Structural Steel Frame | 4/21/2020 | Approved | MARK FERRARI |
| Wood Frame | 4/21/2020 | Corrections Issued | MARK FERRARI |
| Structural Steel Frame | 4/30/2020 | Approved | MARK FERRARI |
| Wood Frame | 4/30/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 5/14/2020 | Corrections Issued | MARK FERRARI |
| Final | 6/25/2020 | Corrections Issued | FELIX CEBALLOS |
| METHANE-Final | 6/25/2020 | Approved | FELIX CEBALLOS |
| SGSOV-Seismic Gas S/O Valve | 6/25/2020 | SGSOV Approved | FELIX CEBALLOS |
| Smoke Detectors | 6/25/2020 | Not Ready for Inspection | FELIX CEBALLOS |
| Final | 8/10/2020 | OK for CofC | VAHE KELEDJIAN |