642 N GRAND AVE 90012

Certificate Information: 642 N GRAND AVE 90012

Application / Permit
19016-10000-07350
Plan Check / Job No.
B19LA05259
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMN
Permit Issued
Issued on 3/12/2020
Issuing Office
Metro
Current Status
CofC Issued on 8/18/2020

Permit Application Status History

Submitted 3/14/2019 APPLICANT
Assigned to Plan Check Engineer 4/10/2019 HANS SANTIAGO
Corrections Issued 4/15/2019 HANS SANTIAGO
Quality Review Completed 4/16/2019 SAI KHUM
Building Plans Picked Up 4/23/2019 APPLICANT
Plan Check Approved 8/20/2019 ANDREW SANTIAGO
Issued 3/12/2020 LADBS
OK for CofC 8/10/2020 VAHE KELEDJIAN
CofC Issued 8/18/2020 ERNESTO CORRAL

Permit Application Clearance Information

Project located in CRA area Cleared 6/18/2019 JIM URQUHART
Housing rent stabilization Cleared 3/9/2020 CHARLES GARCIA

Contact Information

Contractor American Retrofitters Corp; Lic. No.: 1020382-A 15643 SHERMAN WAY STE 220      VAN NUYS, CA 91406
Engineer Au,, Chi-Ming; Lic. No.: C44491 8857 ARDENDALE AVE      SAN GABRIEL, CA 91775

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/2/2020 Approved MARK FERRARI
Deputy Steel/Welding 4/13/2020 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 4/16/2020 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 4/17/2020 Approved JOE VELASQUEZ
Structural Steel Frame 4/17/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 4/17/2020 Not Ready for Inspection JOE VELASQUEZ
Deputy Reinf. Concrete 4/20/2020 Conditional Approval MARK FERRARI
Structural Steel Frame 4/21/2020 Approved MARK FERRARI
Wood Frame 4/21/2020 Corrections Issued MARK FERRARI
Structural Steel Frame 4/30/2020 Approved MARK FERRARI
Wood Frame 4/30/2020 Approved MARK FERRARI
Interior/Exterior Lathing 5/14/2020 Corrections Issued MARK FERRARI
Final 6/25/2020 Corrections Issued FELIX CEBALLOS
METHANE-Final 6/25/2020 Approved FELIX CEBALLOS
SGSOV-Seismic Gas S/O Valve 6/25/2020 SGSOV Approved FELIX CEBALLOS
Smoke Detectors 6/25/2020 Not Ready for Inspection FELIX CEBALLOS
Final 8/10/2020 OK for CofC VAHE KELEDJIAN
Smoke Detectors 8/10/2020 Approved VAHE KELEDJIAN