3505 N EAGLE ROCK BLVD 90065
Certificate Information: 3505 N EAGLE ROCK BLVD 90065
- Application / Permit
- 19016-10000-07346
- Plan Check / Job No.
- B19LA05256
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Brewery
- Work Description
- CONVERT (E) RETAIL SPACE INTO BAR/BREWERY PER ZA 2019-4645-CUB (URM BLDG). INCLUDES OUTDOOR DINING.
- Permit Issued
- Issued on 9/3/2021
- Issuing Office
- Current Status
- CofO Issued on 7/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2019 | LAWRENCE QUIRANTE |
| Corrections Issued | 3/26/2019 | LAWRENCE QUIRANTE |
| Quality Review Completed | 3/28/2019 | GARO TELMI |
| Disabled Access Plans Picked Up | 3/29/2019 | APPLICANT |
| Building Plans Picked Up | 4/2/2019 | APPLICANT |
| Applicant returned to address corrections | 1/25/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 1/26/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 3/8/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 3/9/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 4/28/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 5/24/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 6/9/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 6/29/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 7/19/2021 | LAWRENCE QUIRANTE |
| Plan Check Approved | 7/28/2021 | LAWRENCE QUIRANTE |
| Issued | 9/3/2021 | APPLICANT |
| CofO in Progress | 7/10/2023 | RAFAEL CORTES |
| Permit Finaled | 7/10/2023 | ERNESTO CORRAL |
| CofO Issued | 7/10/2023 | ERNESTO CORRAL |
| Permit Finaled | 7/10/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 4/26/2019 | RICK TORRES |
| Food establishment approval | Cleared | 9/26/2019 | LACDHS APPROVED |
| DAS Clearance | Cleared | 10/16/2019 | LAWRENCE QUIRANTE |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/8/2019 | ADRIAN CASTRO |
| Food Service Establishment | Cleared | 11/15/2019 | RAMESHBHAIR PATEL |
| Supp. Use District POD/CDO/TDO | Cleared | 11/25/2020 | ADRINEH MELKONIAN |
| Comm Cor/Mini-Mall | Cleared | 1/29/2021 | BRYANT WU |
| Comm Cor/Mini-Mall | Cleared | 1/29/2021 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 2/3/2021 | BRYANT WU |
| Miscellaneous | Cleared | 6/23/2021 | WALLIE JONG |
Contact Information
| Contractor | Tanc And Vogel Construction Llc; Lic. No.: 1031279-B | 1717 W ORANGEWOOD STE I ORANGE, CA 92868 |
| Engineer | Hanbali,, Amjad Moh'D; Lic. No.: C42213 | 514 W COMMERCE AVE STE C PALMDALE, CA 93551 |
| Engineer | Salehi,, Mohammad Reza Tom; Lic. No.: C50447 | P O BOX 17881 ENCINO, CA 91416 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/16/2022 | Corrections Issued | MARK FERRARI |
| Deputy Reinf. Concrete | 5/18/2022 | Conditional Approval | MARK FERRARI |
| Drywall Nailing | 6/2/2022 | Partial Approval | MARK FERRARI |
| Insulation | 6/2/2022 | Partial Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 6/6/2022 | Conditional Approval | ERNESTO CORRAL |
| Wood Frame | 6/8/2022 | Partial Approval | MARK FERRARI |
| Wood Frame | 7/11/2022 | Partial Inspection | MARK FERRARI |
| Wood Frame | 7/14/2022 | Partial Approval | MARK FERRARI |
| Drywall Nailing | 7/22/2022 | Partial Approval | MARK FERRARI |
| Final | 5/11/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Reinforced Masonry Frame | 5/11/2023 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 5/11/2023 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 5/11/2023 | Approved | RAFAEL CORTES |
| Final | 5/25/2023 | Corrections Issued | RAFAEL CORTES |
| Reinforced Masonry Frame | 5/25/2023 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 5/25/2023 | SGSOV Not Ready | RAFAEL CORTES |
| Final | 6/22/2023 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 6/22/2023 | SGSOV Approved | RAFAEL CORTES |
| Final | 7/10/2023 | OK to Issue CofO | RAFAEL CORTES |