3646 S KEYSTONE AVE 90034
Certificate Information: 3646 S KEYSTONE AVE 90034
- Application / Permit
- 19016-10000-06706
- Plan Check / Job No.
- B19LA04847
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL (2) MOMENT FRAMES AND (1) SCCS.
- Permit Issued
- Issued on 1/27/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 4/27/2020
Permit Application Status History
| Submitted | 3/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/3/2019 | EVERARDO SANTOS |
| Corrections Issued | 4/10/2019 | EVERARDO SANTOS |
| Quality Review Completed | 4/16/2019 | SAI KHUM |
| Building Plans Picked Up | 4/23/2019 | APPLICANT |
| Plan Check Approved | 9/3/2019 | EVERARDO SANTOS |
| Issued | 1/27/2020 | LADBS |
| OK for CofC | 4/23/2020 | PAUL DAVIDSON |
| CofC Issued | 4/27/2020 | TED RIES |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/5/2019 | SOPHIE GABEL-SCHEINBAU |
| Housing rent stabilization | Cleared | 12/16/2019 | MICHAEL SOTO |
Contact Information
| Contractor | Biayna Corp; Lic. No.: 998853-B | 9751 WHEATLAND AVE SUNLAND, CA 91040 |
| Engineer | Muradyan,, David; Lic. No.: S6232 | 10233 JOHANNA AVE SUNLAND, CA 91040 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/29/2020 | Approved | PAUL DAVIDSON |
| Wood Frame | 1/31/2020 | Corrections Issued | JEFF BYTHEWAY |
| Wood Frame | 2/5/2020 | Partial Inspection | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 2/13/2020 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 2/13/2020 | Approved | PAUL DAVIDSON |
| Structural Steel Frame | 2/13/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Wood Frame | 2/13/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 2/18/2020 | Conditional Approval | PAUL DAVIDSON |
| Structural Steel Frame | 3/6/2020 | Approved | PAUL DAVIDSON |
| Wood Frame | 3/6/2020 | Approved | PAUL DAVIDSON |
| Interior/Exterior Lathing | 3/18/2020 | Approved | JEFF BYTHEWAY |
| Final | 4/23/2020 | OK for CofC | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 4/23/2020 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 4/23/2020 | Approved | PAUL DAVIDSON |