1330 S CENTINELA AVE 90025
Certificate Information: 1330 S CENTINELA AVE 90025
- Application / Permit
- 19016-10000-06665
- Plan Check / Job No.
- B19LA04811
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL SPECIAL STEEL CANTILEVER COLUMNS
- Permit Issued
- Issued on 9/24/2020
- Issuing Office
- Current Status
- CofC Issued on 6/4/2024
Permit Application Status History
| Submitted | 3/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/3/2019 | HANS SANTIAGO |
| Corrections Issued | 4/9/2019 | HANS SANTIAGO |
| Quality Review Completed | 4/10/2019 | SAI KHUM |
| Building Plans Picked Up | 5/10/2019 | APPLICANT |
| Applicant returned to address corrections | 5/31/2019 | HANS SANTIAGO |
| Plan Check Approved | 7/3/2019 | ANDREW SANTIAGO |
| Issued | 9/24/2020 | APPLICANT |
| OK for CofC | 5/13/2024 | RICARDO ROBLES |
| CofC Issued | 6/4/2024 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 9/3/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/30/2022 | Approved | GRANT WOODS |
| Wood Frame | 9/2/2022 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 9/16/2022 | Partial Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 9/23/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 9/27/2022 | Conditional Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 9/29/2022 | Approved | ALAN NOVAK |
| Wood Frame | 9/29/2022 | Approved | ALAN NOVAK |
| Deputy Reinf. Concrete | 10/5/2022 | Conditional Approval | ALAN NOVAK |
| Interior/Exterior Lathing | 10/14/2022 | Approved | ALAN NOVAK |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Not Ready | ALAN NOVAK |
| Final | 11/7/2022 | Corrections Issued | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 11/7/2022 | SGSOV Approved | SORIN CIRSTOIU |
| Smoke Detectors | 11/7/2022 | Partial Inspection | SORIN CIRSTOIU |
| Final | 5/13/2024 | OK for CofC | RICARDO ROBLES |
| Smoke Detectors | 5/13/2024 | Approved | RICARDO ROBLES |