4346 N MAMMOTH AVE 91423
Certificate Information: 4346 N MAMMOTH AVE 91423
- Application / Permit
- 19016-10000-06264
- Plan Check / Job No.
- B19LA04464
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 1 (N) SCCS.
- Permit Issued
- Issued on 4/5/2021
- Issuing Office
- Current Status
- CofC Issued on 10/7/2021
Permit Application Status History
| Submitted | 3/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2019 | EVERARDO SANTOS |
| Corrections Issued | 4/2/2019 | EVERARDO SANTOS |
| Quality Review Completed | 4/4/2019 | SAI KHUM |
| Building Plans Picked Up | 4/5/2019 | APPLICANT |
| Plan Check Approved | 7/22/2019 | EVERARDO SANTOS |
| Issued | 4/5/2021 | APPLICANT |
| OK for CofC | 7/6/2021 | KENNETH ROBERTS |
| CofC Issued | 10/7/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/25/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Tatum Hill Construction; Lic. No.: 1035535-B | 5142 VENICE BLVD LOS ANGELES, CA 90019 |
| Engineer | Ebrahimian, Dehaghani, Mahdi; Lic. No.: C86987 | 8730 COSTA VERDE BLVD APT 2348 SAN DIEGO, CA 92122 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/23/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Reinforced Masonry Frame | 6/3/2021 | Corrections Issued | JOE VELASQUEZ |
| Structural Steel Frame | 6/3/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/3/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Reinforced Concrete Frame | 6/7/2021 | Partial Approval | SORIN CIRSTOIU |
| Structural Steel Frame | 6/7/2021 | Approved | SORIN CIRSTOIU |
| Wood Frame | 6/7/2021 | Partial Approval | SORIN CIRSTOIU |
| Insulation | 6/9/2021 | Approved | JOE VELASQUEZ |
| Wood Frame | 6/10/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Drywall Nailing | 6/11/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/11/2021 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 6/28/2021 | Approved | KENNETH ROBERTS |
| Final | 7/2/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/2/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 7/2/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 7/6/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 7/6/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 7/6/2021 | Approved | KENNETH ROBERTS |