220 N TOLUCA ST 90026

Certificate Information: 220 N TOLUCA ST 90026

Application / Permit
19016-10000-05921
Plan Check / Job No.
B19LA04207
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft Story Retrofit as per LABC Ch. 93. Install 1 OMF and 1 SCCS.
Permit Issued
Issued on 2/12/2020
Issuing Office
Metro
Current Status
CofC Issued on 4/20/2022

Permit Application Status History

Submitted 3/1/2019 APPLICANT
Assigned to Plan Check Engineer 3/14/2019 DANIEL SANJUAN
Corrections Issued 3/19/2019 DANIEL SANJUAN
Quality Review Completed 3/19/2019 HANS SANTIAGO
Building Plans Picked Up 3/22/2019 APPLICANT
Plan Check Approved 4/23/2019 DANIEL SANJUAN
Issued 2/12/2020 LADBS
OK for CofC 4/20/2022 WINSTON DUNNING
CofC Issued 4/20/2022 WINSTON DUNNING

Permit Application Clearance Information

Housing rent stabilization Cleared 7/1/2019 STEVEN HOFSTAD
Abandoned oil well Cleared 12/10/2019 JEREMY CARTER
Abandoned oil well approval Cleared 12/10/2019 JEREMY CARTER

Contact Information

Contractor Retrofitting360 Inc; Lic. No.: 1039226-B 19562 VENTURA BLVD# 230      TARZANA, CA 91356
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/20/2020 Approved BRUCE CAMPBELL
Deputy Drilled-In Anchors 3/6/2020 Conditional Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 3/11/2020 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 3/17/2020 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 3/17/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 3/17/2020 Not Ready for Inspection MARK FERRARI
Excavation/Setback/Form/Re-Bar 3/18/2020 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 3/18/2020 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 3/20/2020 Approved MARK FERRARI
Structural Steel Frame 3/24/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 3/24/2020 Corrections Issued MARK FERRARI
Light Gage Steel Frame 4/21/2020 Not Ready for Inspection MARK FERRARI
Reinforced Concrete Frame 4/21/2020 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 4/21/2020 Approved MARK FERRARI
Wood Frame 4/21/2020 Approved MARK FERRARI
Interior/Exterior Lathing 4/28/2020 Approved FELIX CEBALLOS
Final 6/29/2020 Corrections Issued MARK FERRARI
METHANE-Final 6/29/2020 Approved MARK FERRARI
SGSOV-Seismic Gas S/O Valve 6/29/2020 SGSOV Approved MARK FERRARI
Smoke Detectors 6/29/2020 Approved MARK FERRARI
Final 7/1/2020 Conditional Approval FELIX CEBALLOS
Final 4/20/2022 OK for CofC WINSTON DUNNING