3992 W 8TH ST 90005

Certificate Information: 3992 W 8TH ST 90005

Application / Permit
19016-10000-05910
Plan Check / Job No.
B19LA04195
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL 2 (N) SCCS.
Permit Issued
Issued on 10/21/2020
Issuing Office
Current Status
CofC Issued on 3/1/2021

Permit Application Status History

Submitted 3/1/2019 APPLICANT
Assigned to Plan Check Engineer 3/27/2019 JAIME OROZCO
Corrections Issued 4/3/2019 JAIME OROZCO
Quality Review Completed 4/5/2019 SAI KHUM
Building Plans Picked Up 4/18/2019 APPLICANT
Plan Check Approved 5/24/2019 JAIME OROZCO
Issued 10/21/2020 APPLICANT
OK for CofC 2/23/2021 MARK FERRARI
CofC Issued 3/1/2021 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 10/21/2020 MICHAEL SOTO

Contact Information

Contractor Optimum Seismic Inc; Lic. No.: 1012702-B 5508 S SANTA FE AVENUE      VERNON, CA 90058
Engineer Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 1377 S BEVERLY GLEN BLVD 308      LOS ANGELES, CA 90024

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/4/2020 Approved DARRYL ARNOLD
Deputy Steel/Welding 1/7/2021 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 1/8/2021 Conditional Approval DARRYL ARNOLD
Structural Steel Frame 1/8/2021 Conditional Approval DARRYL ARNOLD
Wood Frame 1/8/2021 Conditional Approval DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 1/12/2021 Approved DARRYL ARNOLD
Wood Frame 1/12/2021 Approved DARRYL ARNOLD
Interior/Exterior Lathing 1/20/2021 Corrections Issued MARK FERRARI
Final 2/12/2021 Conditional Approval JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 2/12/2021 SGSOV Approved JONATHAN QUACH
Smoke Detectors 2/12/2021 Approved JONATHAN QUACH
Final 2/23/2021 OK for CofC MARK FERRARI