5229 N BALBOA BLVD 91316
Certificate Information: 5229 N BALBOA BLVD 91316
- Application / Permit
- 19016-10000-05077
- Plan Check / Job No.
- B19LA03647
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL 6 (N) SCCS AND 11 (N) OMF AND WOOD SHEAR WALLS.
- Permit Issued
- Issued on 9/9/2024
- Issuing Office
- Metro
- Current Status
- Issued on 9/9/2024
Permit Application Status History
| Submitted | 2/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2019 | VARAND SARKISIAN |
| Corrections Issued | 3/27/2019 | VARAND SARKISIAN |
| Quality Review Completed | 3/28/2019 | SAI KHUM |
| Building Plans Picked Up | 4/12/2019 | APPLICANT |
| Applicant returned to address corrections | 8/27/2019 | VARAND SARKISIAN |
| Plan Check Approved | 4/23/2024 | VARAND SARKISIAN |
| Issued | 9/9/2024 | APPLICANT |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 8/20/2024 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Sinai Construction; Lic. No.: 1035535-B | 5142 VENICE BLVD LOS ANGELES, CA 90019 |
| Engineer | Toranzo-Dianderas,, Luis Alberto; Lic. No.: S6014 | 7235 N MAPLE RD VAN NUYS, CA 91405 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/4/2025 | Approved | KENNETH ROBERTS |
| Footing/Foundation/Slab | 6/13/2025 | Approved | KENNETH ROBERTS |
| Structural Steel Frame | 6/13/2025 | Approved | KENNETH ROBERTS |
| Wood Frame | 6/13/2025 | Approved | KENNETH ROBERTS |
| Interior/Exterior Lathing | 6/20/2025 | Partial Approval | JEFFREY DURAN |
| Deputy Drilled-In Anchors | 7/24/2025 | Conditional Approval | GREGORY POMISH |
| Deputy Steel/Welding | 7/24/2025 | Conditional Approval | GREGORY POMISH |
| Deputy Drilled-In Anchors | 7/30/2025 | Conditional Approval | KENNETH ROBERTS |
| Footing/Foundation/Slab | 10/8/2025 | Partial Approval | KENNETH ROBERTS |
| Structural Steel Frame | 10/8/2025 | Partial Approval | KENNETH ROBERTS |
| Wood Frame | 10/8/2025 | Approved | KENNETH ROBERTS |
| Excavation/Setback/Form/Re-Bar | 10/30/2025 | Partial Approval | KENNETH ROBERTS |
| Structural Steel Frame | 10/30/2025 | Partial Approval | KENNETH ROBERTS |
| Wood Frame | 10/30/2025 | Partial Approval | KENNETH ROBERTS |
| Wood Frame | 11/6/2025 | Not Ready for Inspection | BRIAN KELLY |
| Wood Frame | 11/7/2025 | Partial Approval | KENNETH ROBERTS |
| Interior/Exterior Lathing | 11/21/2025 | Partial Approval | KENNETH ROBERTS |
| Interior/Exterior Lathing | 12/1/2025 | Partial Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 12/11/2025 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 12/11/2025 | Conditional Approval | JEFFREY DURAN |
| Excavation/Setback/Form/Re-Bar | 12/17/2025 | Partial Approval | KENNETH ROBERTS |
| Structural Steel Frame | 12/17/2025 | Approved | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 12/29/2025 | Conditional Approval | KENNETH ROBERTS |
| Interior/Exterior Lathing | 12/30/2025 | Partial Approval | KENNETH ROBERTS |
| Structural Steel Frame | 1/14/2026 | Approved | KENNETH ROBERTS |
| Wood Frame | 1/14/2026 | Approved | KENNETH ROBERTS |