3761 S HILL ST 90007
Certificate Information: 3761 S HILL ST 90007
- Application / Permit
- 19016-10000-04741
- Plan Check / Job No.
- B19LA03427
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (22) Warehouse
- Work Description
- CHANGE OF USE TO PORTION OF EXISTING OFFICES ON 2ND FLOOR TO LIVE/WORK UNITS AS PER ZA-2016-3524-ZAD.
- Permit Issued
- Issued on 1/28/2022
- Issuing Office
- Current Status
- CofO Issued on 5/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2019 | ERIC WONG |
| Corrections Issued | 3/5/2019 | ERIC WONG |
| Quality Review Completed | 4/23/2019 | LAURA DUONG |
| Disabled Access Plans Picked Up | 8/30/2019 | APPLICANT |
| Applicant returned to address corrections | 2/21/2020 | ERIC WONG |
| Plan Check Approved | 1/12/2022 | ERIC WONG |
| Issued | 1/28/2022 | APPLICANT |
| Building Plans Picked Up | 2/18/2022 | APPLICANT |
| CofO in Progress | 4/19/2023 | ALAN MORELOS |
| Permit Finaled | 5/3/2023 | ERNESTO CORRAL |
| CofO Issued | 5/3/2023 | ERNESTO CORRAL |
| Permit Finaled | 5/3/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2020 | JEANIE LAM |
| Sewer availability | Cleared | 1/7/2020 | JEANIE LAM |
| DAS Clearance | Cleared | 2/12/2020 | ERIC WONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2020 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 3/5/2020 | JEREMY CARTER |
| Green Code | Cleared | 6/28/2021 | AARON COSTA |
| Fire Marshall Fire Life Safety | Cleared | 10/7/2021 | DOMINIQUE MEDINA |
| Miscellaneous | Cleared | 11/19/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 11/19/2021 | RUBEN VASQUEZ |
| Project located in CRA area | Cleared | 12/7/2021 | DAVID URITA |
Contact Information
| Architect | Segal,, Barry William; Lic. No.: C17861 | P O BOX 6108 ALTADENA, CA 91003 |
| Contractor | Owner-Builder | , |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/19/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Insulation | 4/27/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 5/11/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 6/3/2022 | Corrections Issued | MARK FERRARI |
| Drywall Nailing | 6/7/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 6/28/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 7/8/2022 | Conditional Approval | ERNESTO CORRAL |
| Footing/Foundation/Slab | 7/19/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Reinforced Concrete Frame | 7/19/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 7/21/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 7/22/2022 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 7/22/2022 | Partial Approval | GREGORY POMISH |
| Deputy Steel/Welding | 8/8/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 8/9/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 8/10/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 8/12/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 8/15/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 8/30/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 8/31/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 9/1/2022 | Conditional Approval | WINSTON DUNNING |
| Insulation | 9/2/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 9/6/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Steel/Welding | 9/7/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Steel/Welding | 9/9/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 9/22/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Insulation | 9/22/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 9/23/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 9/28/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 9/30/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 9/30/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 10/3/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 10/4/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 10/5/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 10/6/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 10/7/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 10/27/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 10/28/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 11/1/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 11/4/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Structural Steel Frame | 11/10/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Not Ready for Inspection | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 12/12/2022 | Partial Approval | ALAN MORELOS |
| Drywall Nailing | 12/28/2022 | Partial Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Partial Approval | ALAN MORELOS |
| Excavation/Setback/Form/Re-Bar | 1/17/2023 | Partial Approval | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 1/24/2023 | Partial Approval | ALAN MORELOS |
| Deputy Reinf. Concrete | 1/31/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 2/8/2023 | Conditional Approval | ALAN MORELOS |
| Deputy Steel/Welding | 2/8/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 2/10/2023 | Conditional Approval | ALAN MORELOS |
| Deputy Steel/Welding | 2/16/2023 | Conditional Approval | ALAN MORELOS |
| Deputy Steel/Welding | 2/21/2023 | Conditional Approval | ALAN MORELOS |
| Drywall Nailing | 2/22/2023 | Partial Approval | MARTIN TAVITIAN |
| Deputy Steel/Welding | 2/23/2023 | Conditional Approval | ALAN MORELOS |
| Drywall Nailing | 2/24/2023 | Approved | MARTIN TAVITIAN |
| Deputy Steel/Welding | 2/27/2023 | Conditional Approval | ALAN MORELOS |
| Deputy Steel/Welding | 3/1/2023 | Conditional Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Approved | ALAN MORELOS |
| Structural Steel Frame | 3/2/2023 | Approved | ALAN MORELOS |
| Final | 3/10/2023 | Partial Inspection | ALAN MORELOS |
| Green Building Final | 3/10/2023 | Partial Inspection | ALAN MORELOS |
| Green Building Rough | 3/10/2023 | Partial Inspection | ALAN MORELOS |
| Reinforced Masonry Frame | 3/10/2023 | Partial Inspection | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 3/10/2023 | SGSOV Not Ready | ALAN MORELOS |
| Smoke Detectors | 3/10/2023 | Partial Inspection | ALAN MORELOS |
| Final | 3/21/2023 | Not Ready for Inspection | ALAN MORELOS |
| Green Building Final | 3/21/2023 | Approved | ALAN MORELOS |
| Green Building Rough | 3/21/2023 | Approved | ALAN MORELOS |
| Reinforced Masonry Frame | 3/21/2023 | Approved | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 3/21/2023 | SGSOV Approved | ALAN MORELOS |
| Smoke Detectors | 3/21/2023 | Not Ready for Inspection | ALAN MORELOS |
| Final | 4/19/2023 | OK to Issue CofO | ALAN MORELOS |
| Smoke Detectors | 4/19/2023 | Approved | ALAN MORELOS |