10654 N IRMA AVE 91042

Certificate Information: 10654 N IRMA AVE 91042

Application / Permit
19016-10000-04486
Plan Check / Job No.
B19LA03273
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
(see comments)EXTERIOR AND INTERIOR TI OF EXISTING PUBLIC POOL HOUSE, NEW LANDSCAPING AND NEW/REMODELED EXTERIOR ADA RAMPS; (parking restriping)NO CHANGE IN OCCUPANCY. GRADING and SHORING ARE UNDER SEPARATE PERMITS.
Permit Issued
Issued on 1/22/2024
Issuing Office
Metro
Current Status
Permit Finaled on 8/11/2025

Permit Application Status History

Submitted 2/15/2019 APPLICANT
Assigned to Plan Check Engineer 3/8/2019 MINA HABIB
Corrections Issued 3/12/2019 EMMANUEL MARTINEZ
Quality Review Completed 3/13/2019 ARMEN JIVALAGIAN
Building Plans Picked Up 3/15/2019 APPLICANT
Applicant returned to address corrections 9/3/2020 MINA HABIB
Green Plans Picked Up 9/29/2020 APPLICANT
Applicant returned to address corrections 10/13/2020 MINA HABIB
Applicant returned to address corrections 10/20/2020 MINA HABIB
Applicant returned to address corrections 10/23/2020 MINA HABIB
Disabled Access Plans Picked Up 2/2/2021 APPLICANT
Applicant returned to address corrections 7/30/2021 MINA HABIB
Applicant returned to address corrections 8/12/2021 MINA HABIB
Applicant returned to address corrections 9/30/2021 MINA HABIB
Applicant returned to address corrections 12/3/2021 MINA HABIB
Applicant returned to address corrections 1/11/2022 MINA HABIB
Applicant returned to address corrections 2/17/2022 MINA HABIB
Applicant returned to address corrections 2/22/2022 MINA HABIB
Applicant returned to address corrections 3/15/2022 MINA HABIB
Applicant returned to address corrections 3/17/2022 MINA HABIB
Applicant returned to address corrections 7/29/2022 MINA HABIB
Applicant returned to address corrections 8/31/2022 MINA HABIB
Applicant returned to address corrections 10/13/2022 MINA HABIB
Applicant returned to address corrections 1/19/2023 MINA HABIB
Applicant returned to address corrections 2/23/2023 MINA HABIB
Applicant returned to address corrections 1/11/2024 MINA HABIB
Plan Check Approved 1/18/2024 MINA HABIB
Issued 1/22/2024 APPLICANT
Permit Finaled 8/11/2025 ANDREW DORSO

Permit Application Clearance Information

City owned building/parcel Cleared 8/17/2020 HAROOT AVANESIAN
Roof/Waste drainage to street Cleared 8/20/2020 GUILLERMO PETRA
Sewer availability Cleared 8/20/2020 GUILLERMO PETRA
Green Code Cleared 9/17/2020 COLIN LOREDO
DAS Clearance Cleared 11/10/2021 EMMANUEL MARTINEZ
Grading Pre-Inspection Cleared 7/29/2022 EMMANUEL MARTINEZ
Eng Process Fee Ord 176,300 Cleared 3/9/2023 RYAN KIM

Contact Information

Architect Del, Poso, Celso Jimenez; Lic. No.: C29974 15331 THIONNET PLACE      MOORPARK, CA 93021
Contractor Pars Arvin Construction Inc; Lic. No.: 804404-B 6119 TAMPA AVE      TARZANA, CA 913356640
Engineer Bhalja,, Manan; Lic. No.: S6573 4983 GLENVIEW STREET      CHINO HILLS, CA 91709
Engineer Forcier,, Easton Rene; Lic. No.: GE2948 233 TULANE ROAD      COSTA MESA, CA 92626
Engineer Lam,, Gary; Lic. No.: C65208 1518 MANLEY DR      SAN GABRIEL, CA 91776

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/8/2024 Corrections Issued ANDREW DORSO
Deputy Drilled-In Anchors 5/7/2024 Conditional Approval KENNETH ROBERTS
Deputy Drilled-In Anchors 5/8/2024 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 5/14/2024 Partial Inspection ANDREW DORSO
Piling/Pier/Caisson 5/24/2024 Partial Approval JOHN KITCKO
Light Gage Steel Frame 5/30/2024 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 6/5/2024 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 6/11/2024 Conditional Approval ANDREW DORSO
Excavation/Setback/Form/Re-Bar 6/13/2024 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 6/17/2024 Approved ANDREW DORSO
Deputy Drilled-In Anchors 6/21/2024 Conditional Approval KENNETH ROBERTS
Footing/Foundation/Slab 6/24/2024 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 6/27/2024 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 6/27/2024 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 7/8/2024 Partial Inspection ANDREW DORSO
Insulation 7/8/2024 Approved ANDREW DORSO
Light Gage Steel Frame 7/8/2024 Approved ANDREW DORSO
Drywall Nailing 7/16/2024 Approved ANDREW DORSO
Footing/Foundation/Slab 8/14/2024 Corrections Issued ANDREW DORSO
Footing/Foundation/Slab 8/15/2024 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 8/21/2024 Approved ANDREW DORSO
Footing/Foundation/Slab 8/29/2024 Not Ready for Inspection BRIAN KELLY
Footing/Foundation/Slab 8/30/2024 Partial Approval ROBERT DAVIS
Insulation 9/20/2024 Approved KENNETH ROBERTS
Deputy Drilled-In Anchors 9/27/2024 Approved ANDREW DORSO
Footing/Foundation/Slab 9/27/2024 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 10/11/2024 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 10/16/2024 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 10/18/2024 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 10/23/2024 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 10/24/2024 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 10/25/2024 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 10/25/2024 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 11/8/2024 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 11/14/2024 Conditional Approval ANDREW DORSO
Deputy Drilled-In Anchors 11/21/2024 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 11/22/2024 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 11/26/2024 Not Ready for Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 12/2/2024 Partial Approval JOHN KITCKO
Light Gage Steel Frame 12/5/2024 Approved ANDREW DORSO
Deputy Drilled-In Anchors 12/9/2024 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 12/9/2024 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 12/10/2024 Partial Inspection ANDREW DORSO
Drywall Nailing 12/13/2024 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 1/8/2025 Not Ready for Inspection ANDREW DORSO
Piling/Pier/Caisson 1/9/2025 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 2/24/2025 Partial Inspection ANDREW DORSO
Pre-Inspection 2/26/2025 Not Ready for Inspection ANDREW DORSO
Deputy Drilled-In Anchors 3/26/2025 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 3/27/2025 Partial Inspection ANDREW DORSO
Drywall Nailing 4/7/2025 Partial Approval KENNETH ROBERTS
Final 8/11/2025 Permit Finaled ANDREW DORSO
Green Building Final 8/11/2025 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 8/11/2025 SGSOV Approved ANDREW DORSO
Smoke Detectors 8/11/2025 Approved ANDREW DORSO