330 S HOPE ST 2ND FLOOR 90071
Certificate Information: 330 S HOPE ST 2ND FLOOR 90071
- Application / Permit
- 19016-10000-04432
- Plan Check / Job No.
- B19LA03218
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- PROPOSED CHANGE OF USE 8,717 USF OF OFFICE SPACE TO A RESTAURANT, GYM AND DINING AREA; NO OUTDOOR DINING
- Permit Issued
- Issued on 8/16/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2019 | SINA KHOSRAVI |
| Green Plans Picked Up | 2/28/2019 | APPLICANT |
| Corrections Issued | 3/3/2019 | SINA KHOSRAVI |
| Quality Review Completed | 3/14/2019 | FELIX FIGUEROA |
| Building Plans Picked Up | 3/19/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 3/19/2019 | APPLICANT |
| Applicant returned to address corrections | 6/12/2019 | SINA KHOSRAVI |
| Plan Check Approved | 7/31/2019 | SINA KHOSRAVI |
| Issued | 8/16/2019 | LADBS |
| TCO Issued (Expire Date: 05-29-2021) | 11/30/2020 | DAVID TSAU |
| CofO in Progress | 3/9/2021 | KATY RAMIREZ |
| CofO Issued | 3/10/2021 | DAVID TSAU |
| Permit Finaled | 3/10/2021 | DAVID TSAU |
Permit Application Clearance Information
| Food Service Establishment | Cleared | 5/30/2019 | RAMESHBHAIR PATEL |
| Green Code | Cleared | 6/5/2019 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2019 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 6/7/2019 | ADRIAN SANCHEZ |
| DAS Clearance | Cleared | 7/10/2019 | ELIZABETH TOMS |
| Fire Marshall Fire Life Safety | Cleared | 7/24/2019 | WILLIAM JOHNS |
| Specific Plan | Cleared | 7/24/2019 | JOE LUCKEY |
| ZA Case | Cleared | 7/24/2019 | JOE LUCKEY |
| Food establishment approval | Cleared | 7/31/2019 | LACDHS APPROVED |
Contact Information
| Contractor | Coastline Development Inc; Lic. No.: 485187-B | 13911 ENTERPRISE DRIVE GARDEN GROVE, CA 92843 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/20/2019 | Approved | KATY RAMIREZ |
| Light Gage Steel Frame | 1/27/2020 | Partial Inspection | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 3/10/2020 | Conditional Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 3/13/2020 | Partial Approval | KATY RAMIREZ |
| Insulation | 3/16/2020 | Approved | LANNY MERRICK |
| Light Gage Steel Frame | 4/17/2020 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 4/23/2020 | Partial Approval | KATY RAMIREZ |
| Special/Order Compliance | 4/30/2020 | Partial Inspection | DANIEL COLLINS |
| Drywall Nailing | 5/4/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 5/4/2020 | Partial Approval | DANIEL COLLINS |
| Special/Order Compliance | 5/12/2020 | Approved | DANIEL COLLINS |
| Drywall Nailing | 5/28/2020 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 5/28/2020 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 6/2/2020 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 6/5/2020 | Partial Approval | KATY RAMIREZ |
| T-Bar Ceiling | 6/30/2020 | Conditional Approval | DANIEL COLLINS |
| Drywall Nailing | 7/2/2020 | Approved | KATY RAMIREZ |
| Pre-Inspection | 9/17/2020 | Approved | KATY RAMIREZ |
| Pre-Inspection | 10/5/2020 | Partial Inspection | DANIEL COLLINS |
| Pre-Inspection | 10/13/2020 | No Access for Inspection | KATY RAMIREZ |
| Pre-Inspection | 10/14/2020 | Partial Inspection | KATY RAMIREZ |
| Pre-Inspection | 10/16/2020 | Approved | KATY RAMIREZ |
| Pre-Inspection | 2/12/2021 | Approved | KATY RAMIREZ |
| Final | 3/4/2021 | Partial Inspection | KATY RAMIREZ |
| Green Building Final | 3/4/2021 | Approved | KATY RAMIREZ |
| Green Building Rough | 3/4/2021 | Approved | KATY RAMIREZ |
| Reinforced Concrete Frame | 3/4/2021 | Partial Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 3/4/2021 | SGSOV Approved | KATY RAMIREZ |
| Smoke Detectors | 3/4/2021 | Approved | KATY RAMIREZ |
| Final | 3/10/2021 | OK to Issue CofO | KATY RAMIREZ |
| Reinforced Concrete Frame | 3/10/2021 | Approved | KATY RAMIREZ |