1629 N GRIFFITH PARK BLVD 90026

Certificate Information: 1629 N GRIFFITH PARK BLVD 90026

Application / Permit
19016-10000-04103
Plan Check / Job No.
B19LA02961
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
Change of use from (E) Church (per permit 1931LA16702) to Hotel/Restaurant and bar, new elevators and roof structure as per ZA-2013-69-CU-CUB-ZAA.
Permit Issued
Issued on 6/6/2022
Issuing Office
Current Status
CofO Issued on 5/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2019 APPLICANT
Assigned to Plan Check Engineer 2/28/2019 DEAN LEE
Corrections Issued 3/6/2019 DEAN LEE
Quality Review Completed 3/18/2019 BILL STUTSMAN
Building Plans Picked Up 3/20/2019 APPLICANT
Applicant returned to address corrections 7/2/2019 DEAN LEE
Applicant returned to address corrections 11/6/2019 DEAN LEE
Applicant returned to address corrections 8/3/2021 RODOLFO ARIAS
Plan Check Approved 6/2/2022 RODOLFO ARIAS
Issued 6/6/2022 APPLICANT
CofO in Progress 5/6/2026 LUIS CCAMACHO
Permit Finaled 5/8/2026 ADAM BURGESS
CofO Issued 5/8/2026 ADAM BURGESS
Permit Finaled 5/8/2026 ADAM BURGESS

Permit Application Clearance Information

"Q" conditions Cleared 3/29/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 3/29/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 3/29/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 7/5/2019 SOPHIE GABEL-SCHEINBAU
Eng Process Fee Ord 176,300 Cleared 11/17/2020 CELINA MORENO
Address approval Cleared 11/18/2020 CELINA MORENO
Highway dedication Cleared 11/23/2020 CELINA MORENO
Sewer availability Cleared 3/16/2021 CELINA MORENO
Hydrant and Access approval Cleared 4/21/2021 MATTHEW CRAIG
Fire Marshall Fire Life Safety Cleared 8/20/2021 VIDAL GARCIA
Construction near power lines Cleared 9/10/2021 TINA MIRANDA
GPI Written Notices Cleared 9/15/2021 RODOLFO ARIAS
Grading Pre-Inspection Cleared 9/15/2021 RODOLFO ARIAS
DAS Clearance Cleared 12/15/2021 DEAN LEE
Food Service Establishment Cleared 12/16/2021 PAWAN VERMA
Green Code Cleared 12/23/2021 AARON COSTA
Food establishment approval Cleared 1/17/2022 LACDHS APPROVED
Building over 36-ft Cleared 2/16/2022 CALOSHA APPROVED
Low Impact Development Cleared 2/28/2022 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 3/3/2022 ABEL CASILLAS

Contact Information

Architect Bartholomew,, Lucia; Lic. No.: C37422 4116 PINE HOLLOW RD      CALABASAS, CA 91302
Contractor City Constructors Inc; Lic. No.: 834591-B 450 S RAYMOND AVENUE      PASADENA, CA 91105
Engineer Rybak,, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803
Landscape Architect Howell,, Dean Edward; Lic. No.: LA5765 851 N OGDEN DR      LOS ANGELES, CA 90046

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/8/2022 Conditional Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 6/10/2022 Not Ready for Inspection JONATHAN QUACH
Footing/Foundation/Slab 6/10/2022 Not Ready for Inspection JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 6/14/2022 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 6/14/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/16/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 6/16/2022 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 6/16/2022 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 7/1/2022 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 7/1/2022 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/28/2022 Partial Approval JONATHAN QUACH
Deputy Reinf. Concrete 8/2/2022 Conditional Approval WINSTON DUNNING
Deputy Steel/Welding 8/2/2022 Conditional Approval WINSTON DUNNING
Excavation/Setback/Form/Re-Bar 8/9/2022 Partial Approval MARK FERRARI
Footing/Foundation/Slab 8/9/2022 Partial Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 8/31/2022 Partial Approval TIMOTHY BUXTON
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Approved TIMOTHY BUXTON
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Approved JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Not Ready for Inspection JONATHAN QUACH
Deputy Reinf. Concrete 9/13/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 9/15/2022 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 9/19/2022 Partial Approval JONATHAN QUACH
Green Building Rough 9/20/2022 Not Ready for Inspection JONATHAN QUACH
Wood Frame 9/20/2022 Partial Approval JONATHAN QUACH
Pre-Inspection 9/27/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Insulation 10/14/2022 Corrections Issued JONATHAN QUACH
Deputy Steel/Welding 10/27/2022 Conditional Approval MICHAEL ROSENBERG
Insulation 10/28/2022 Partial Approval JONATHAN QUACH
Deputy Steel/Welding 11/7/2022 Conditional Approval MICHAEL ROSENBERG
Insulation 11/7/2022 Partial Approval JONATHAN QUACH
Insulation 11/30/2022 Partial Inspection ALFREDO LOPEZ
Deputy Wood Construction 12/9/2022 Conditional Approval TIMOTHY POWELL
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 12/14/2022 Partial Approval RAMAZANALI ALMASI
Insulation 12/20/2022 Corrections Issued RONALD JIMENEZ
Drywall Nailing 12/29/2022 Partial Approval TIMOTHY POWELL
Insulation 1/24/2023 Corrections Issued TIMOTHY POWELL
Green Building Rough 1/26/2023 Approved RONALD JIMENEZ
Wood Frame 1/26/2023 Partial Approval RONALD JIMENEZ
Drywall Nailing 1/30/2023 Partial Approval RONALD JIMENEZ
Special/Order Compliance 1/30/2023 Corrections Issued RONALD JIMENEZ
Light Gage Steel Frame 2/7/2023 Partial Approval TIMOTHY POWELL
Wood Frame 2/7/2023 Partial Approval TIMOTHY POWELL
Drywall Nailing 2/10/2023 Partial Approval TIMOTHY POWELL
Insulation 2/14/2023 Partial Approval TIMOTHY POWELL
Drywall Nailing 2/22/2023 Partial Approval TIMOTHY POWELL
Interior/Exterior Lathing 2/22/2023 Partial Approval TIMOTHY POWELL
Light Gage Steel Frame 2/22/2023 Partial Approval TIMOTHY POWELL
Insulation 4/6/2023 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 4/6/2023 Partial Approval RONALD JIMENEZ
Drywall Nailing 4/19/2023 Partial Approval TIMOTHY POWELL
Light Gage Steel Frame 4/19/2023 Partial Approval TIMOTHY POWELL
Drywall Nailing 4/25/2023 Partial Approval TIMOTHY POWELL
Drywall Nailing 6/14/2023 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 5/29/2024 Not Ready for Inspection RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 6/3/2024 Partial Approval RAFAEL CORTES
Insulation 6/21/2024 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 6/26/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 7/3/2024 Approved MARTIN TAVITIAN
Light Gage Steel Frame 7/29/2024 Partial Approval RAMAZANALI ALMASI
Insulation 8/12/2024 Partial Approval RAMAZANALI ALMASI
Wood Frame 8/13/2024 Approved RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Not Ready for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 8/26/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 9/3/2024 Partial Inspection JEROME BLACKWOOD
Pre-Inspection 9/3/2024 Partial Inspection JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 9/5/2024 No Access for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 9/6/2024 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 9/6/2024 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 9/9/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 9/12/2024 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Partial Inspection RAFAEL CORTES
Light Gage Steel Frame 9/17/2024 Partial Approval LUIS CCAMACHO
Pre-Inspection 9/17/2024 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 9/19/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 9/24/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 9/24/2024 Corrections Issued LUIS CCAMACHO
Light Gage Steel Frame 9/26/2024 Partial Approval LUIS CCAMACHO
Insulation 10/1/2024 Partial Approval LUIS CCAMACHO
Interior/Exterior Lathing 10/3/2024 Not Ready for Inspection JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 10/7/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 10/7/2024 Partial Approval LUIS CCAMACHO
Interior/Exterior Lathing 10/9/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 10/15/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 10/21/2024 Partial Inspection LUIS CCAMACHO
Drywall Nailing 10/29/2024 Partial Approval LUIS CCAMACHO
Special/Order Compliance 10/29/2024 Partial Inspection LUIS CCAMACHO
Drywall Nailing 11/1/2024 Partial Approval LUIS CCAMACHO
Excavation/Setback/Form/Re-Bar 11/1/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 11/6/2024 Not Ready for Inspection LUIS CCAMACHO
Excavation/Setback/Form/Re-Bar 11/13/2024 Partial Approval LUIS CCAMACHO
Excavation/Setback/Form/Re-Bar 11/21/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 11/26/2024 Partial Approval LUIS CCAMACHO
Masonry Wall/Backfill 11/26/2024 Not Ready for Inspection LUIS CCAMACHO
Masonry Wall/Backfill 12/2/2024 Partial Approval LUIS CCAMACHO
Insulation 12/6/2024 Not Ready for Inspection LUIS CCAMACHO
Special/Order Compliance 12/6/2024 Not Ready for Inspection LUIS CCAMACHO
Masonry Wall/Backfill 12/10/2024 Not Ready for Inspection LUIS CCAMACHO
Drywall Nailing 12/12/2024 Partial Approval RAMAZANALI ALMASI
Masonry Wall/Backfill 12/12/2024 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 12/17/2024 Partial Approval LUIS CCAMACHO
Excavation/Setback/Form/Re-Bar 12/19/2024 Partial Approval LUIS CCAMACHO
Insulation 12/19/2024 Not Ready for Inspection LUIS CCAMACHO
Wood Frame 12/23/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 12/31/2024 Not Ready for Inspection LUIS CCAMACHO
Drywall Nailing 1/2/2025 Partial Approval LUIS CCAMACHO
Insulation 1/2/2025 Partial Approval LUIS CCAMACHO
Pre-Inspection 1/3/2025 Partial Inspection JEROME BLACKWOOD
Drywall Nailing 1/6/2025 Not Ready for Inspection LUIS CCAMACHO
Excavation/Setback/Form/Re-Bar 1/6/2025 Partial Approval LUIS CCAMACHO
Drywall Nailing 1/10/2025 Partial Approval MARTIN TAVITIAN
Drywall Nailing 1/15/2025 Partial Approval LUIS CCAMACHO
Drywall Nailing 1/27/2025 Partial Approval LUIS CCAMACHO
Interior/Exterior Lathing 1/31/2025 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 2/4/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 2/6/2025 Partial Approval LUIS CCAMACHO
Pre-Inspection 2/18/2025 Partial Inspection LUIS CCAMACHO
T-Bar Ceiling 2/21/2025 Partial Approval LUIS CCAMACHO
Reinforced Concrete Frame 3/11/2025 Partial Approval LUIS CCAMACHO
Drywall Nailing 3/12/2025 Partial Approval LUIS CCAMACHO
Drywall Nailing 4/1/2025 Partial Approval LUIS CCAMACHO
Special/Order Compliance 5/5/2025 Partial Approval LUIS CCAMACHO
Pre-Inspection 6/12/2025 Partial Inspection LUIS CCAMACHO
Final 6/20/2025 Not Ready for Inspection RAFAEL CORTES
Green Building Final 6/20/2025 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 6/20/2025 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 6/20/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 6/20/2025 Not Ready for Inspection RAFAEL CORTES
Final 6/25/2025 Not Ready for Inspection LUIS CCAMACHO
Green Building Final 6/25/2025 Approved LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Approved LUIS CCAMACHO
Smoke Detectors 6/25/2025 Approved LUIS CCAMACHO
Wood Frame 6/25/2025 Approved LUIS CCAMACHO
Special/Order Compliance 6/26/2025 Corrections Issued LUIS CCAMACHO
Pre-Inspection 4/9/2026 Partial Approval LUIS CCAMACHO
Final 5/6/2026 OK to Issue CofO LUIS CCAMACHO