1017 W M ST 90744

Certificate Information: 1017 W M ST 90744

Application / Permit
19016-10000-03998
Plan Check / Job No.
B19LA02866
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND REC ROOM TO NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 AND ADDITION/EXTERIOR REMODEL
Permit Issued
Issued on 10/3/2019
Issuing Office
San Pedro
Current Status
CofO Issued on 3/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2019 APPLICANT
Assigned to Plan Check Engineer 2/12/2019 EMMANUEL MARTINEZ
Corrections Issued 2/15/2019 CHIHARU SUZUKI
Plan Check Approved 8/27/2019 KEVIN MORALES
Issued 10/3/2019 LADBS
CofO in Progress 3/9/2026 EUGENE CASSIDY
Permit Finaled 3/10/2026 ANSON MAGLASANG
CofO Issued 3/10/2026 ANSON MAGLASANG
Permit Finaled 3/10/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/28/2019 ELENA LOPEZ
Roof/Waste drainage to street Cleared 3/28/2019 ELENA LOPEZ
ZA Case Cleared 3/28/2019 BLAYNE SUTTON-WILLS
ZI Cleared 3/28/2019 BLAYNE SUTTON-WILLS
Eng Process Fee Ord 176,300 Cleared 3/29/2019 ADRIAN SANCHEZ
Sewer availability Cleared 3/29/2019 ADRIAN SANCHEZ
Construction near power lines Cleared 8/12/2019 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Chu,, Tien Manh; Lic. No.: C72324 9542 PACIFIC AVE      ANAHEIM, CA 92804

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/26/2019 Conditional Approval JOHN KLARIN
Excavation/Setback/Form/Re-Bar 12/4/2019 Corrections Issued JOHN KLARIN
Excavation/Setback/Form/Re-Bar 12/6/2019 Approved JOHN KLARIN
Footing/Foundation/Slab 12/6/2019 Conditional Approval JOHN KLARIN
METHANE-Barrier 12/6/2019 Approved JOHN KLARIN
METHANE-Subgrade 12/6/2019 Approved JOHN KLARIN
PLUMBING-Rough 12/31/2019 Partial Inspection JOHN KLARIN
BUILDING-Rough-Frame 2/27/2020 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 2/27/2020 Corrections Issued JOHN KLARIN
HVAC-Rough 2/27/2020 Corrections Issued JOHN KLARIN
METHANE-Rough 2/27/2020 Approved JOHN KLARIN
PLUMBING-Rough 2/27/2020 Approved JOHN KLARIN
PLUMBING-Rough 3/3/2020 Not Ready for Inspection JOHN KLARIN
Underground Mechanical 3/3/2020 Approved JOHN KLARIN
Insulation 11/20/2020 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 2/12/2026 Approved EUGENE CASSIDY
Final 2/12/2026 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 2/12/2026 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/12/2026 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 2/12/2026 Approved EUGENE CASSIDY
Final 2/27/2026 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/27/2026 SGSOV Approved EUGENE CASSIDY
ELECTRICAL-Final 3/6/2026 Approved EUGENE CASSIDY
Final 3/6/2026 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 3/6/2026 Approved EUGENE CASSIDY
PLUMBING-Final 3/6/2026 Approved EUGENE CASSIDY