13933 W OXNARD ST 91401
Certificate Information: 13933 W OXNARD ST 91401
- Application / Permit
- 19016-10000-03763
- Plan Check / Job No.
- B19LA02690
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CH. 93. INSTALL STEEL MOMENT FRAME.
- Permit Issued
- Issued on 6/4/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 4/13/2021
Permit Application Status History
| Submitted | 2/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2019 | CLARIS RIVERA |
| Corrections Issued | 3/14/2019 | CLARIS RIVERA |
| Quality Review Completed | 3/22/2019 | SAI KHUM |
| Building Plans Picked Up | 4/5/2019 | APPLICANT |
| Applicant returned to address corrections | 5/3/2019 | CLARIS RIVERA |
| Plan Check Approved | 5/21/2019 | MANUEL MONTUFAR |
| Issued | 6/4/2020 | LADBS |
| OK for CofC | 3/30/2021 | KENNETH ROBERTS |
| CofC Issued | 4/13/2021 | RICKEY JACKSON |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 5/3/2019 | CLARIS RIVERA |
| Housing rent stabilization | Cleared | 4/29/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Sheene Paul Corporation; Lic. No.: 1015399-A | 520 SOUTH GRAND AVENUE STE 360 LOS ANGELES, CA 90071 |
| Engineer | Azarbin,, Hamid Reza; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/11/2020 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 6/12/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Pre-Inspection | 6/23/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Pre-Inspection | 7/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 8/6/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 9/1/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 9/1/2020 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 9/2/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 9/2/2020 | Corrections Issued | JOE VELASQUEZ |
| Footing/Foundation/Slab | 9/14/2020 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 9/14/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 9/18/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/18/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 10/27/2020 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 10/29/2020 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 11/6/2020 | Corrections Issued | JONATHAN QUACH |
| Structural Steel Frame | 11/12/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 2/26/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/26/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 2/26/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 3/12/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 3/12/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 3/12/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 3/30/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 3/30/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 3/30/2021 | Approved | KENNETH ROBERTS |