430 S HOLT AVE 90048
Certificate Information: 430 S HOLT AVE 90048
- Application / Permit
- 19016-10000-03673
- Plan Check / Job No.
- B19LA02627
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIR PER LABC CHAPTER 93. INSTALL STEEL MOMENT FRAME
- Permit Issued
- Issued on 8/25/2020
- Issuing Office
- Current Status
- CofC Issued on 7/22/2021
Permit Application Status History
| Submitted | 2/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2019 | MANUEL MONTUFAR |
| Corrections Issued | 3/5/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 3/6/2019 | HANS SANTIAGO |
| Plan Check Approved | 6/28/2019 | MANUEL MONTUFAR |
| Issued | 8/25/2020 | APPLICANT |
| OK for CofC | 7/22/2021 | MARK FERRARI |
| CofC Issued | 7/22/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 8/11/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Jones,, Richard Alan; Lic. No.: S4977 | 5058 VIA INGRESSO YORBA LINDA, CA 92886 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/4/2020 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 9/18/2020 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 9/18/2020 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 9/28/2020 | Approved | JONATHAN QUACH |
| Deputy Reinf. Concrete | 9/30/2020 | Conditional Approval | JONATHAN QUACH |
| Light Gage Steel Frame | 10/22/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 10/22/2020 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/28/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 12/15/2020 | Conditional Approval | JONATHAN QUACH |
| METHANE-Final | 12/15/2020 | Approved | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 12/15/2020 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 12/15/2020 | Approved | JONATHAN QUACH |
| Final | 2/17/2021 | Conditional Approval | JONATHAN QUACH |
| Final | 7/22/2021 | OK for CofC | MARK FERRARI |