12848 W BLOOMFIELD ST 91604
Certificate Information: 12848 W BLOOMFIELD ST 91604
- Application / Permit
- 19016-10000-03644
- Plan Check / Job No.
- B19LA02600
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. 2 OMF.
- Permit Issued
- Issued on 2/6/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 11/12/2020
Permit Application Status History
| Submitted | 2/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2019 | DANIEL SANJUAN |
| Corrections Issued | 3/15/2019 | DANIEL SANJUAN |
| Quality Review Completed | 3/22/2019 | SAI KHUM |
| Building Plans Picked Up | 4/2/2019 | APPLICANT |
| Plan Check Approved | 7/19/2019 | DANIEL SANJUAN |
| Issued | 2/6/2020 | LADBS |
| OK for CofC | 11/12/2020 | ERNESTO CORRAL |
| CofC Issued | 11/12/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/6/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | L A Retrofit Inc; Lic. No.: 1047943-B | 818 7TH STREET APARTMENT 2 SANTA MONICA, CA 90403 |
| Engineer | Farmand,, Anthony E; Lic. No.: C62595 | 2372 MORSE AVE STE 137 IRVINE, CA 92614 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| SGSOV-Seismic Gas S/O Valve | 7/10/2020 | SGSOV Not Ready | VAHE KELEDJIAN |
| Pre-Inspection | 7/15/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 8/12/2020 | Partial Approval | JOE VELASQUEZ |
| Insulation | 8/13/2020 | Corrections Issued | JOE VELASQUEZ |
| Footing/Foundation/Slab | 9/16/2020 | Approved | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 9/17/2020 | No Access for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/30/2020 | Partial Approval | JOE VELASQUEZ |
| Wood Frame | 10/5/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 10/7/2020 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 10/14/2020 | Approved | JOE VELASQUEZ |
| Final | 10/21/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/21/2020 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 10/21/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 10/29/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/29/2020 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 10/29/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 11/12/2020 | OK for CofC | ERNESTO CORRAL |
| SGSOV-Seismic Gas S/O Valve | 11/12/2020 | SGSOV Approved | ERNESTO CORRAL |
| Smoke Detectors | 11/12/2020 | Approved | ERNESTO CORRAL |