412 S SEATON ST 90013

Certificate Information: 412 S SEATON ST 90013

Application / Permit
19016-10000-03375
Plan Check / Job No.
B19LA02427
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Dance Hall
Work Description
CHANGE OF USE / OCCUPANCY FROM WAREHOUSE TO BANQUET HALL . RESTRIPE THE PARKING LOT
Permit Issued
Issued on 9/1/2022
Issuing Office
Current Status
CofO Issued on 5/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2019 APPLICANT
Assigned to Plan Check Engineer 2/21/2019 HERNAN ARREOLA
Disabled Access Plans Picked Up 2/22/2019 APPLICANT
Corrections Issued 3/4/2019 MOHAMMAD FIROUZBAKHT
Quality Review Completed 3/7/2019 FELIX FIGUEROA
Green Plans Picked Up 3/28/2019 APPLICANT
Applicant returned to address corrections 4/30/2019 HERNAN ARREOLA
Applicant returned to address corrections 5/22/2019 HERNAN ARREOLA
Applicant returned to address corrections 5/23/2019 HERNAN ARREOLA
Applicant returned to address corrections 5/30/2019 HERNAN ARREOLA
Applicant returned to address corrections 9/3/2019 HERNAN ARREOLA
Plan Check Approved 11/12/2019 HERNAN ARREOLA
Issued 9/1/2022 APPLICANT
Building Plans Picked Up 9/8/2022 APPLICANT
CofO in Progress 5/6/2025 RONALD JIMENEZ
CofO Issued 5/12/2025 ERNESTO CORRAL
Permit Finaled 5/12/2025 ERNESTO CORRAL

Permit Application Clearance Information

Permit Cleared 3/15/2019 ADRIAN SANCHEZ
Trees in Parkway Cleared 3/19/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 4/12/2019 ADRIAN SANCHEZ
ZA Case Cleared 5/30/2019 ANNA VAN
Sewer availability Cleared 6/13/2019 ELAINE LEI
DAS Clearance Cleared 6/20/2019 MOHAMMAD FIROUZBAKHT
DAS Clearance Cleared 6/20/2019 WAI LAU
Green Code Cleared 6/28/2019 KHEDER ALRAZAA
Fire Marshall Fire Life Safety Cleared 10/23/2019 WILLIAM JOHNS
Low Impact Development Cleared 11/7/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 11/7/2019 ERIK BEASLEY

Contact Information

Architect , ; Lic. No.: C37802 1107 FAIR OAKS AVE #137      SOUTH PASADENA, CA 91030
Contractor Driver S P G Llc; Lic. No.: 960119-B 468 NORTH ROSEMEAD BLVD      PASADENA, CA 91107
Engineer Garza,, Omar Leonel; Lic. No.: S5593 4215 TOLAND WAY      LOS ANGELES, CA 90065

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 4/19/2023 Partial Approval JULIAN CAPUCETTI
Pre-Inspection 4/19/2023 Approved JULIAN CAPUCETTI
Excavation/Setback/Form/Re-Bar 7/13/2023 Partial Approval JULIAN CAPUCETTI
Footing/Foundation/Slab 7/13/2023 Partial Approval JULIAN CAPUCETTI
Green Building Rough 7/20/2023 Not Ready for Inspection JULIAN CAPUCETTI
METHANE-Rough 7/20/2023 Not Ready for Inspection JULIAN CAPUCETTI
Reinforced Concrete Frame 7/20/2023 Partial Approval JULIAN CAPUCETTI
Green Building Rough 8/2/2023 Not Ready for Inspection JULIAN CAPUCETTI
METHANE-Rough 8/2/2023 Not Ready for Inspection JULIAN CAPUCETTI
Reinforced Concrete Frame 8/2/2023 Partial Approval JULIAN CAPUCETTI
Green Building Rough 8/23/2023 Not Ready for Inspection JULIAN CAPUCETTI
METHANE-Rough 8/23/2023 Not Ready for Inspection JULIAN CAPUCETTI
Masonry Wall/Backfill 8/23/2023 Partial Approval JULIAN CAPUCETTI
Reinforced Masonry Frame 8/23/2023 Partial Approval JULIAN CAPUCETTI
Deputy Drilled-In Anchors 8/29/2023 Conditional Approval JULIAN CAPUCETTI
Green Building Rough 9/7/2023 Partial Approval JULIAN CAPUCETTI
METHANE-Rough 9/7/2023 Partial Approval JULIAN CAPUCETTI
Reinforced Concrete Frame 9/7/2023 Partial Approval JULIAN CAPUCETTI
Footing/Foundation/Slab 9/15/2023 Partial Inspection RONALD JIMENEZ
Green Building Rough 9/15/2023 Not Ready for Inspection RONALD JIMENEZ
METHANE-Rough 9/15/2023 Not Ready for Inspection RONALD JIMENEZ
Structural Steel Frame 10/5/2023 Not Ready for Inspection LARRY ARNICK
Green Building Rough 10/10/2023 Not Ready for Inspection RAFAEL CORTES
METHANE-Rough 10/10/2023 Approved RAFAEL CORTES
Reinforced Concrete Frame 10/10/2023 Partial Approval RAFAEL CORTES
Green Building Rough 10/12/2023 Not Ready for Inspection RAMAZANALI ALMASI
Reinforced Concrete Frame 10/12/2023 Partial Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 11/15/2023 Partial Approval RAMAZANALI ALMASI
Deputy Reinf. Concrete 11/16/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 11/27/2023 Approved JACOB MYERS
Light Gage Steel Frame 12/6/2023 Not Ready for Inspection KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 1/30/2024 Partial Approval MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 2/26/2024 Partial Approval RAMAZANALI ALMASI
Floor/Roof Diaphrgm/Shear Wall 3/5/2024 Partial Approval RONALD JIMENEZ
Green Building Rough 3/5/2024 Approved RONALD JIMENEZ
Insulation 3/5/2024 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 3/7/2024 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 4/9/2024 Partial Approval RONALD JIMENEZ
Drywall Nailing 4/12/2024 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 4/12/2024 Partial Approval RONALD JIMENEZ
Footing/Foundation/Slab 4/12/2024 Partial Approval RONALD JIMENEZ
Insulation 4/12/2024 Partial Approval RONALD JIMENEZ
Drywall Nailing 4/16/2024 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 4/16/2024 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 4/22/2024 Partial Approval RONALD JIMENEZ
Pre-Inspection 5/13/2024 Approved RONALD JIMENEZ
Pre-Inspection 6/10/2024 Approved RONALD JIMENEZ
Insulation 6/20/2024 Partial Approval RONALD JIMENEZ
Pre-Inspection 6/26/2024 Approved RONALD JIMENEZ
Drywall Nailing 7/2/2024 Partial Approval RONALD JIMENEZ
Pre-Inspection 7/11/2024 Approved RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 7/24/2024 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 7/30/2024 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 8/1/2024 Partial Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 8/19/2024 Partial Approval RONALD JIMENEZ
Deputy Fireproofing 8/26/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Fireproofing 8/28/2024 Conditional Approval RAMAZANALI ALMASI
Pre-Inspection 9/27/2024 Not Ready for Inspection PAUL BAZERKANIAN
Piling/Pier/Caisson 11/1/2024 Partial Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 11/19/2024 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 11/22/2024 Approved RONALD JIMENEZ
Wood Frame 12/3/2024 Partial Approval RONALD JIMENEZ
Drywall Nailing 3/19/2025 Approved RONALD JIMENEZ
Final 3/19/2025 Not Ready for Inspection RONALD JIMENEZ
Green Building Final 3/19/2025 Approved RONALD JIMENEZ
Reinforced Concrete Frame 3/19/2025 Approved RONALD JIMENEZ
Reinforced Masonry Frame 3/19/2025 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 3/19/2025 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 3/19/2025 Not Ready for Inspection RONALD JIMENEZ
Final 5/6/2025 OK to Issue CofO RONALD JIMENEZ
Smoke Detectors 5/6/2025 Approved RONALD JIMENEZ