3358 1/4 N GLENDALE BLVD 90039

Certificate Information: 3358 1/4 N GLENDALE BLVD 90039

Application / Permit
19016-10000-02902
Plan Check / Job No.
B19LA02032
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert exising detached garage to accessory dwelling unit (ADU) per GC65852.2(e)(1)a.
Permit Issued
Issued on 6/4/2020
Issuing Office
Current Status
CofO Corrected on 8/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2019 APPLICANT
Assigned to Plan Check Engineer 2/21/2019 ANA AVELAR
Corrections Issued 2/28/2019 ANA AVELAR
Quality Review Completed 3/20/2019 KESETE HAREGOT
Building Plans Picked Up 4/5/2019 APPLICANT
Plan Check Approved 6/2/2020 TU HUA
Issued 6/4/2020 APPLICANT
CofO in Progress 2/3/2022 HAMIK HARTOUNIAN
CofO Issued-Status Void 2/7/2022 DEROLD HAUFF
Permit Finaled-Status Void 2/7/2022 DEROLD HAUFF
Re-Activate Permit 8/26/2022 DEROLD HAUFF
Permit Finaled 8/27/2022 DEROLD HAUFF
CofO Corrected 8/27/2022 DEROLD HAUFF
Permit Finaled 8/27/2022 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 3/10/2020 DANIEL CORONADO
Address approval Cleared 3/10/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 3/10/2020 CECILIO NAVARRO
Sewer availability Cleared 3/10/2020 CECILIO NAVARRO
Supp. Use District POD/CDO/TDO Cleared 3/10/2020 DANIEL CORONADO
ZI Cleared 3/10/2020 DANIEL CORONADO
ZI Cleared 3/10/2020 DANIEL CORONADO
Roof/Waste drainage to street Cleared 4/29/2020 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Sarrami,, Gholamali F; Lic. No.: C43720 4942 HIGHLAND VIEW AVENUE      LOS ANGELES, CA 90041

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/18/2020 Approved HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 5/12/2021 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/2/2021 Approved HAMIK HARTOUNIAN
Wood Frame 7/7/2021 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 7/23/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 7/27/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Corrections Issued BRIAN SULLIVAN
Insulation 9/2/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/2/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 9/22/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/22/2021 Approved HAMIK HARTOUNIAN
Final 11/3/2021 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/3/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 11/3/2021 Approved HAMIK HARTOUNIAN
Wood Frame 11/3/2021 Approved HAMIK HARTOUNIAN
Final 12/2/2021 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 12/2/2021 SGSOV Approved HAMIK HARTOUNIAN
Final 2/2/2022 OK to Issue CofO HAMIK HARTOUNIAN