3358 1/4 N GLENDALE BLVD 90039
Certificate Information: 3358 1/4 N GLENDALE BLVD 90039
- Application / Permit
- 19016-10000-02902
- Plan Check / Job No.
- B19LA02032
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert exising detached garage to accessory dwelling unit (ADU) per GC65852.2(e)(1)a.
- Permit Issued
- Issued on 6/4/2020
- Issuing Office
- Current Status
- CofO Corrected on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2019 | ANA AVELAR |
| Corrections Issued | 2/28/2019 | ANA AVELAR |
| Quality Review Completed | 3/20/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 4/5/2019 | APPLICANT |
| Plan Check Approved | 6/2/2020 | TU HUA |
| Issued | 6/4/2020 | APPLICANT |
| CofO in Progress | 2/3/2022 | HAMIK HARTOUNIAN |
| CofO Issued-Status Void | 2/7/2022 | DEROLD HAUFF |
| Permit Finaled-Status Void | 2/7/2022 | DEROLD HAUFF |
| Re-Activate Permit | 8/26/2022 | DEROLD HAUFF |
| Permit Finaled | 8/27/2022 | DEROLD HAUFF |
| CofO Corrected | 8/27/2022 | DEROLD HAUFF |
| Permit Finaled | 8/27/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 3/10/2020 | DANIEL CORONADO |
| Address approval | Cleared | 3/10/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 3/10/2020 | CECILIO NAVARRO |
| Supp. Use District POD/CDO/TDO | Cleared | 3/10/2020 | DANIEL CORONADO |
| ZI | Cleared | 3/10/2020 | DANIEL CORONADO |
| ZI | Cleared | 3/10/2020 | DANIEL CORONADO |
| Roof/Waste drainage to street | Cleared | 4/29/2020 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/18/2020 | Approved | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 5/12/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 6/2/2021 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 7/7/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Wood Frame | 7/23/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 7/27/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2021 | Corrections Issued | BRIAN SULLIVAN |
| Insulation | 9/2/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/2/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/22/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/22/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 11/3/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 11/3/2021 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/3/2021 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 11/3/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 12/2/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2021 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 2/2/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |