684 S MATEO ST 90021

Certificate Information: 684 S MATEO ST 90021

Application / Permit
19016-10000-02767
Plan Check / Job No.
B19LA01918
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
PROPOSED CHANGE OF USE OF AN EXISTING (77'-4" X 257'-4") WAREHOUSE TO OFFICE AND RETAIL(TOTAL 4 TENANTS 1 OFFICE & 3 RETAIL). WORK INLCUDES MINOR INTERIOR DEMOLITION, INTERIOR PATITIONS, SUSPEND CEILINGS, AND MILLWORK. ***hours of operation from 7am to 11pm***
Permit Issued
Issued on 9/3/2019
Issuing Office
Metro
Current Status
CofO Issued on 6/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2019 APPLICANT
Assigned to Plan Check Engineer 2/7/2019 MICHAEL LOPEZ
Corrections Issued 2/13/2019 MICHAEL LOPEZ
Quality Review Completed 2/21/2019 FELIX FIGUEROA
Building Plans Picked Up 2/27/2019 APPLICANT
Green Plans Picked Up 2/27/2019 APPLICANT
Disabled Access Plans Picked Up 3/12/2019 APPLICANT
Applicant returned to address corrections 5/2/2019 MICHAEL LOPEZ
Applicant returned to address corrections 5/8/2019 MICHAEL LOPEZ
Applicant returned to address corrections 5/16/2019 MICHAEL LOPEZ
Applicant returned to address corrections 5/31/2019 MICHAEL LOPEZ
Applicant returned to address corrections 7/25/2019 MICHAEL LOPEZ
Applicant returned to address corrections 7/31/2019 MICHAEL LOPEZ
Plan Check Approved 8/14/2019 MICHAEL LOPEZ
Issued 9/3/2019 LADBS
CofO in Progress 6/4/2021 LANNY MERRICK
CofO Issued 6/8/2021 ERNESTO CORRAL
Permit Finaled 6/8/2021 ERNESTO CORRAL

Permit Application Clearance Information

Hold Cleared 2/19/2019 LOURDES RAMIRO
Eng Process Fee Ord 176,300 Cleared 4/3/2019 ERIK BEASLEY
Sewer availability Cleared 4/3/2019 ERIK BEASLEY
ZI Cleared 4/3/2019 BLAYNE SUTTON-WILLS
Comm Cor/Mini-Mall Cleared 4/10/2019 BLAYNE SUTTON-WILLS
Comm Cor/Mini-Mall Cleared 4/10/2019 BLAYNE SUTTON-WILLS
DAS Clearance Cleared 5/7/2019 ELIZABETH TOMS
Project located in CRA area Cleared 5/9/2019 JIM URQUHART
Green Code Cleared 5/13/2019 SARAH ABOULHOSN
Internal circulation Cleared 5/14/2019 MOHAMMAD HASAN
Encroachment in public way Cleared 7/25/2019 ELENA LOPEZ

Contact Information

Contractor A G & B Construction Inc; Lic. No.: 891681-B 923 BALDWIN PARK BLVD      BALDWIN PARK, CA 91706
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 9/9/2019 Partial Inspection JEFFREY FULTON
Wood Frame 9/9/2019 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 10/2/2019 Partial Inspection JEFFREY FULTON
Wood Frame 10/2/2019 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 10/3/2019 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 10/3/2019 Conditional Approval JEFFREY FULTON
Drywall Nailing 10/10/2019 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 10/10/2019 Partial Inspection JEFFREY FULTON
Special/Order Compliance 10/10/2019 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 10/24/2019 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 10/24/2019 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 10/24/2019 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/27/2020 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 1/29/2020 Not Ready for Inspection RONALD PACHECO
Footing/Foundation/Slab 2/5/2020 Partial Approval RONALD PACHECO
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Partial Approval RONALD PACHECO
Interior/Exterior Lathing 5/15/2020 Partial Approval RONALD PACHECO
Final 5/26/2020 Not Ready for Inspection RONALD PACHECO
Green Building Final 5/26/2020 Not Ready for Inspection RONALD PACHECO
Green Building Rough 5/26/2020 Not Ready for Inspection RONALD PACHECO
Reinforced Masonry Frame 5/26/2020 Not Ready for Inspection RONALD PACHECO
SGSOV-Seismic Gas S/O Valve 5/26/2020 SGSOV Not Ready RONALD PACHECO
Smoke Detectors 5/26/2020 Not Ready for Inspection RONALD PACHECO
Final 8/31/2020 Not Ready for Inspection RONALD PACHECO
Green Building Final 8/31/2020 Not Ready for Inspection RONALD PACHECO
Green Building Rough 8/31/2020 Not Ready for Inspection RONALD PACHECO
Reinforced Masonry Frame 8/31/2020 Not Ready for Inspection RONALD PACHECO
SGSOV-Seismic Gas S/O Valve 8/31/2020 SGSOV Not Ready RONALD PACHECO
Smoke Detectors 8/31/2020 Not Ready for Inspection RONALD PACHECO
Final 9/23/2020 Not Ready for Inspection RONALD PACHECO
Green Building Final 9/23/2020 Not Ready for Inspection RONALD PACHECO
Green Building Rough 9/23/2020 Approved RONALD PACHECO
Reinforced Masonry Frame 9/23/2020 Not Ready for Inspection RONALD PACHECO
SGSOV-Seismic Gas S/O Valve 9/23/2020 SGSOV Not Ready RONALD PACHECO
Smoke Detectors 9/23/2020 Not Ready for Inspection RONALD PACHECO
Final 9/25/2020 Not Ready for Inspection RONALD PACHECO
Green Building Final 9/25/2020 Not Ready for Inspection RONALD PACHECO
Reinforced Masonry Frame 9/25/2020 Approved RONALD PACHECO
SGSOV-Seismic Gas S/O Valve 9/25/2020 SGSOV Approved RONALD PACHECO
Smoke Detectors 9/25/2020 Approved RONALD PACHECO
Final 10/2/2020 Not Ready for Inspection LANNY MERRICK
Green Building Final 10/2/2020 Not Ready for Inspection LANNY MERRICK
Final 10/5/2020 Not Ready for Inspection RONALD PACHECO
Green Building Final 10/5/2020 Not Ready for Inspection RONALD PACHECO
Final 5/5/2021 Not Ready for Inspection LANNY MERRICK
Green Building Final 5/5/2021 Not Ready for Inspection LANNY MERRICK
Final 5/24/2021 Not Ready for Inspection LANNY MERRICK
Green Building Final 5/24/2021 Partial Inspection LANNY MERRICK
Final 6/4/2021 OK to Issue CofO LANNY MERRICK
Green Building Final 6/4/2021 Approved LANNY MERRICK