8328 N LOUISE AVE 91325

Certificate Information: 8328 N LOUISE AVE 91325

Application / Permit
19016-10000-02622
Plan Check / Job No.
B19LA01827
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 3/5/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/30/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2019 APPLICANT
Assigned to Plan Check Engineer 1/29/2019 CHIHARU SUZUKI
Corrections Issued 1/29/2019 CHIHARU SUZUKI
Plan Check Approved 3/4/2020 FARSHAD ALIMOHAMADI
Issued 3/5/2020 LADBS
CofO in Progress 12/15/2020 CHRISTOPHE COCHRAN
CofO in Progress 12/15/2020 CHRISTOPHE COCHRAN
CofO Issued 12/30/2020 MICHAEL SMITH
Permit Finaled 12/30/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/6/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/6/2020 LEE GUILBEAUX
Sewer availability Cleared 1/6/2020 LEE GUILBEAUX
ZA Case Cleared 1/6/2020 MARITZA PRZEKOP
Public Works-Highway Ded. Cleared 1/6/2020 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/15/2020 Partial Inspection DANIEL ORRANTE
ELECTRICAL-Rough 6/5/2020 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 6/5/2020 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 6/18/2020 Corrections Issued MARK JOHNSON
PLUMBING-Rough 6/18/2020 Corrections Issued MARK JOHNSON
ELECTRICAL-Final 6/23/2020 Not Ready for Inspection PIERRE VEGA
PLUMBING-Final 6/23/2020 Not Ready for Inspection PIERRE VEGA
ELECTRICAL-Rough 6/30/2020 Approved MARK JOHNSON
PLUMBING-Rough 6/30/2020 Approved MARK JOHNSON
HVAC-Rough 7/10/2020 No Access for Inspection ROBERT MINASSIANS
BUILDING-Rough-Frame 7/13/2020 Approved MARK JOHNSON
Green Building Rough 7/13/2020 Approved MARK JOHNSON
HVAC-Rough 7/13/2020 Approved MARK JOHNSON
MERV13>=Rough 7/13/2020 Approved MARK JOHNSON
Insulation 7/16/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 7/16/2020 Approved MARK JOHNSON
Drywall Nailing 8/6/2020 Approved MARK JOHNSON
Shower Pan 8/6/2020 Approved MARK JOHNSON
Final 10/21/2020 Not Ready for Inspection MARK JOHNSON
Smoke Detectors 10/21/2020 Not Ready for Inspection MARK JOHNSON
Final 11/2/2020 Corrections Issued MARK JOHNSON
Smoke Detectors 11/2/2020 Approved MARK JOHNSON
Final 11/9/2020 OK to Issue CofO MARK JOHNSON