1115 W 190TH ST 90248
Certificate Information: 1115 W 190TH ST 90248
- Application / Permit
- 19016-10000-02582
- Plan Check / Job No.
- B19LA01771
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Bakery
- Work Description
- CHANGE OF USE FROM SHOP/OFFICE/ PARKING TO BAKERY/BAKERY GOODS DISTRIBUTOR WITH INCIDENTAL RETAIL, TENANT IMPROVEMENT OF THE 1ST AND 2ND FLOOR OF THE 2 STORY BUILDING, ADD NEW ELEVATOR, REBUILD INTERIOR STAIR AND MECHANICAL UNIT PLATFORM ON ROOF TOP,( UPTO #1500 PER UNIT)
- Permit Issued
- Issued on 8/6/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/29/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 2/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2019 | SAM CHANG |
| Green Plans Picked Up | 2/8/2019 | APPLICANT |
| Corrections Issued | 2/12/2019 | SAM CHANG |
| Quality Review Completed | 2/28/2019 | QUAN NGHIEM |
| Building Plans Picked Up | 3/4/2019 | APPLICANT |
| Applicant returned to address corrections | 4/9/2019 | SAM CHANG |
| Applicant returned to address corrections | 5/15/2019 | SAM CHANG |
| Plan Check Approved | 8/6/2019 | SAM CHANG |
| Issued | 8/6/2019 | LADBS |
| CofO in Progress | 10/26/2020 | JOEY BUCHANAN |
| Permit Finaled | 10/29/2020 | NICK LAROCCA |
| CofO Issued | 10/29/2020 | NICK LAROCCA |
| Permit Finaled | 10/29/2020 | NICK LAROCCA |
Permit Application Clearance Information
| CPC | Cleared | 3/11/2019 | JOE LUCKEY |
| ZA Case | Cleared | 3/11/2019 | JOE LUCKEY |
| DAS Clearance | Cleared | 4/26/2019 | SHINE LIN |
| Green Code | Cleared | 5/1/2019 | SARAH ABOULHOSN |
| Miscellaneous | Cleared | 5/8/2019 | VIDAL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2019 | ERIK BEASLEY |
| Work Adjacent to Public Way | Cleared | 6/7/2019 | PHILLIP WILSON |
| Sewer availability | Cleared | 7/17/2019 | ERIK BEASLEY |
| Food establishment approval | Cleared | 8/6/2019 | LACDHS APPROVED |
Contact Information
| Architect | Banuelos,, Timothy J; Lic. No.: C27086 | 2325 ESTRELLA COURT PINOLE, CA 94564 |
| Contractor | Alta Construction Incorporated; Lic. No.: 890027-B | 369 E BLAINE STREET CORONA, CA 92879 |
| Engineer | Sierra,, Jesus Francisco; Lic. No.: S3298 | 39812 MISSION BOULEVARD SUITE 100 FREMONT, CA 94539 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/7/2019 | Conditional Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 11/18/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 11/20/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 11/27/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 11/27/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 12/2/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 12/5/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 12/11/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 12/11/2019 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 12/18/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 12/23/2019 | Approved | RAFAEL ESPINOZA |
| Masonry Wall/Backfill | 1/3/2020 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2020 | Partial Approval | RAFAEL ESPINOZA |
| Masonry Wall/Backfill | 1/8/2020 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Masonry | 1/9/2020 | Approved | RAFAEL ESPINOZA |
| Masonry Wall/Backfill | 1/10/2020 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 1/10/2020 | Partial Approval | RAFAEL ESPINOZA |
| Pre-Inspection | 2/19/2020 | Partial Approval | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 3/2/2020 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 3/3/2020 | Approved | JOEY BUCHANAN |
| Wood Frame | 3/4/2020 | Corrections Issued | JOEY BUCHANAN |
| Wood Frame | 3/10/2020 | Partial Approval | JOEY BUCHANAN |
| Light Gage Steel Frame | 4/23/2020 | Corrections Issued | JOEY BUCHANAN |
| Light Gage Steel Frame | 4/29/2020 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 5/19/2020 | Approved | JOEY BUCHANAN |
| T-Bar Ceiling | 6/4/2020 | Approved | NICK LAROCCA |
| Final | 10/22/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 10/22/2020 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 10/22/2020 | Approved | JOEY BUCHANAN |
| Special/Order Compliance | 10/22/2020 | Approved | JOEY BUCHANAN |
| Final | 10/23/2020 | Conditional Approval | JOEY BUCHANAN |
| Green Building Final | 10/23/2020 | Approved | JOEY BUCHANAN |
| Green Building Rough | 10/23/2020 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 10/23/2020 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 10/23/2020 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 10/23/2020 | Approved | JOEY BUCHANAN |