10336 W LANARK ST 91352
Certificate Information: 10336 W LANARK ST 91352
- Application / Permit
- 19016-10000-02532
- Plan Check / Job No.
- B19LA01746
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE/STORAGE INTO AN ACCESSORY DWELLING PER GCS65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/14/2021
- Issuing Office
- Current Status
- CofO Issued on 4/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2019 | MICHAEL LOPEZ |
| Corrections Issued | 2/1/2019 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 6/19/2021 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 7/13/2021 | RICARDO RAMIREZ |
| Building Plans Picked Up | 7/14/2021 | APPLICANT |
| Issued | 9/14/2021 | APPLICANT |
| CofO in Progress | 2/29/2024 | DAVID ANDERSON |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
| CofO Issued | 4/10/2024 | RUBEN SALAS |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2019 | JEANIE LAM |
| Sewer availability | Cleared | 4/2/2019 | JEANIE LAM |
| Construction near power lines | Cleared | 6/28/2021 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/14/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 2/14/2022 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/9/2022 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 3/9/2022 | Partial Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 3/9/2022 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 3/14/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/14/2022 | Approved | GREGG CUMMINGS |
| Special/Order Compliance | 3/14/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/26/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 5/26/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| MERV13>=Rough | 5/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/26/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 6/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 6/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 6/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 6/3/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 6/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 9/14/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 9/14/2022 | Approved | DAVID ANDERSON |
| Drywall Nailing | 11/7/2022 | Approved | DAVID ANDERSON |
| Shower Pan | 11/30/2022 | Approved | DAVID ANDERSON |
| Sewer | 6/8/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 6/8/2023 | Approved | DAVID ANDERSON |
| Final | 12/15/2023 | Corrections Issued | DAVID ANDERSON |
| MERV13>=Final | 12/15/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 12/15/2023 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 12/15/2023 | Approved | DAVID ANDERSON |
| Final | 1/10/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 2/28/2024 | OK to Issue CofO | DAVID ANDERSON |