- Work Description
- SOFT STORY RETROFIT PER LABC CH. 93 INSTALL STEEL MOMENT FRAMES
- Permit Issued
- Issued on 6/9/2021
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/10/2021
Permit Application Status History
| Submitted | 1/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2019 | MANUEL MONTUFAR |
| Corrections Issued | 2/20/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 2/22/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 2/27/2019 | APPLICANT |
| Plan Check Approved | 3/12/2019 | MANUEL MONTUFAR |
| Issued | 6/9/2021 | APPLICANT |
| OK for CofC | 10/7/2021 | KENNETH ROBERTS |
| CofC Issued | 12/10/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 6/2/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Private Builders Inc; Lic. No.: 985586-B | 4730 WOODMAN AVE SUITE 360 SHERMAN OAKS, CA 91423 |
| Engineer | Mnatsakanyan,, Arthur; Lic. No.: C74802 | 4730 WOODMAN AVE STE 360 SHERMAN OAKS, CA 91423 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/29/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 7/6/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 7/7/2021 | Approved | JOE VELASQUEZ |
| Deputy Steel/Welding | 7/7/2021 | Approved | JOE VELASQUEZ |
| Deputy Steel/Welding | 7/8/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 7/9/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 7/16/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 7/19/2021 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 7/19/2021 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 7/19/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/19/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 7/21/2021 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 7/21/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/21/2021 | Corrections Issued | JOE VELASQUEZ |
| Insulation | 8/26/2021 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 8/26/2021 | Approved | JOE VELASQUEZ |
| Wood Frame | 8/26/2021 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 9/9/2021 | Approved | KENNETH ROBERTS |
| Final | 10/7/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 10/7/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 10/7/2021 | Approved | KENNETH ROBERTS |