1130-1132 S CLARK DR 90035

Certificate Information: 1130-1132 S CLARK DR 90035

Application / Permit
19016-10000-02384
Plan Check / Job No.
B19LA01640
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL 4 SCCS.
Permit Issued
Issued on 5/12/2021
Issuing Office
Current Status
OK for CofC on 11/4/2021

Permit Application Status History

Submitted 1/25/2019 APPLICANT
Assigned to Plan Check Engineer 2/21/2019 EVERARDO SANTOS
Corrections Issued 3/4/2019 EVERARDO SANTOS
Quality Review Completed 3/7/2019 HANS SANTIAGO
Building Plans Picked Up 3/13/2019 APPLICANT
Applicant returned to address corrections 10/29/2019 EVERARDO SANTOS
Plan Check Approved 10/31/2019 EVERARDO SANTOS
Issued 5/12/2021 APPLICANT
OK for CofC 11/3/2021 DARRYL ARNOLD

Permit Application Clearance Information

Housing rent stabilization Cleared 2/25/2021 STEVEN HOFSTAD

Contact Information

Contractor Ariel Muller; Lic. No.: 1026822-B 525 N FULLER AVE      LOS ANGELES, CA 90036
Engineer Kim,, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/13/2021 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 6/25/2021 Conditional Approval BRUCE CAMPBELL
Excavation/Setback/Form/Re-Bar 6/25/2021 Approved BRUCE CAMPBELL
Excavation/Setback/Form/Re-Bar 6/28/2021 Approved BRUCE CAMPBELL
Wood Frame 7/13/2021 Partial Approval BRUCE CAMPBELL
Wood Frame 7/20/2021 Approved DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Not Ready for Inspection BRUCE CAMPBELL
Floor/Roof Diaphrgm/Shear Wall 8/10/2021 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 8/18/2021 Corrections Issued BRUCE CAMPBELL
Interior/Exterior Lathing 8/20/2021 Not Ready for Inspection BRUCE CAMPBELL
Interior/Exterior Lathing 8/26/2021 Corrections Issued MARK FERRARI
Final 11/3/2021 Conditional Approval DARRYL ARNOLD
METHANE-Final 11/3/2021 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 11/3/2021 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 11/3/2021 Approved DARRYL ARNOLD
Special/Order Compliance 11/4/2021 Conditional Approval DARRYL ARNOLD
Special/Order Compliance 2/3/2023 Corrections Issued DARRYL ARNOLD