701 N HILL PL 90012
Certificate Information: 701 N HILL PL 90012
- Application / Permit
- 19016-10000-02245
- Plan Check / Job No.
- B19LA01560
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL TWO (N) SPECIAL STEEL CANTILEVER COLUMNS
- Permit Issued
- Issued on 5/11/2020
- Issuing Office
- Current Status
- CofC Issued on 7/27/2020
Permit Application Status History
| Submitted | 1/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2019 | HANS SANTIAGO |
| Corrections Issued | 2/28/2019 | HANS SANTIAGO |
| Quality Review Completed | 3/1/2019 | SAI KHUM |
| Building Plans Picked Up | 3/7/2019 | APPLICANT |
| Plan Check Approved | 3/20/2019 | Andrew Santiago |
| Issued | 5/11/2020 | APPLICANT |
| OK for CofC | 7/23/2020 | VAHE KELEDJIAN |
| CofC Issued | 7/27/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 3/19/2019 | JIM URQUHART |
| Housing rent stabilization | Cleared | 5/5/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/15/2020 | Approved | FELIX CEBALLOS |
| Deputy Steel/Welding | 5/22/2020 | Partial Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 5/27/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 5/28/2020 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 5/28/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 5/28/2020 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 6/1/2020 | No Access for Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 6/3/2020 | Approved | DARRYL ARNOLD |
| Final | 7/7/2020 | Not Ready for Inspection | VAHE KELEDJIAN |
| METHANE-Final | 7/7/2020 | Approved | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 7/7/2020 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 7/7/2020 | Not Ready for Inspection | VAHE KELEDJIAN |
| Final | 7/23/2020 | OK for CofC | VAHE KELEDJIAN |
| Smoke Detectors | 7/23/2020 | Approved | VAHE KELEDJIAN |