1342 W 227TH ST 90501

Certificate Information: 1342 W 227TH ST 90501

Application / Permit
19016-10000-02244
Plan Check / Job No.
B19LA01558
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY SEISMIC RETROFIT PER LABC CHAPTER 93. INSTALL 1 STEEL SPECIAL CANTILEVERE COLUMN SYSTEM AND PLYWOOD SHEAR WALLS.
Permit Issued
Issued on 12/9/2020
Issuing Office
Current Status
CofC Issued on 3/11/2021

Permit Application Status History

Submitted 1/24/2019 APPLICANT
Assigned to Plan Check Engineer 2/21/2019 ERWIN PASCUA
Corrections Issued 2/25/2019 ERWIN PASCUA
Quality Review Completed 2/27/2019 MARJAN SHENASI
Building Plans Picked Up 3/7/2019 APPLICANT
Applicant returned to address corrections 4/11/2019 ERWIN PASCUA
Plan Check Approved 11/23/2020 DANIEL SANJUAN
Issued 12/9/2020 APPLICANT
OK for CofC 3/9/2021 JOEY BUCHANAN
CofC Issued 3/11/2021 NICK LAROCCA

Permit Application Clearance Information

Housing rent stabilization Cleared 12/8/2020 STEVEN HOFSTAD

Contact Information

Contractor Retrofitting360 Inc; Lic. No.: 1039226-B 19562 VENTURA BLVD# 230      TARZANA, CA 91356
Engineer Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 1377 S BEVERLY GLEN BLVD 308      LOS ANGELES, CA 90024

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/7/2021 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 1/12/2021 Approved JOEY BUCHANAN
Deputy Steel/Welding 1/13/2021 Approved JOEY BUCHANAN
Footing/Foundation/Slab 2/1/2021 Approved LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 2/17/2021 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 2/19/2021 Not Ready for Inspection JOEY BUCHANAN
Structural Steel Frame 2/19/2021 Approved JOEY BUCHANAN
Wood Frame 2/19/2021 Approved JOEY BUCHANAN
Structural Steel Frame 2/24/2021 Approved JOEY BUCHANAN
Wood Frame 2/24/2021 Approved JOEY BUCHANAN
Interior/Exterior Lathing 3/2/2021 Approved JOEY BUCHANAN
Final 3/9/2021 OK for CofC JOEY BUCHANAN
METHANE-Final 3/9/2021 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 3/9/2021 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 3/9/2021 Approved JOEY BUCHANAN