4117 N ACKERMAN DR 90065

Certificate Information: 4117 N ACKERMAN DR 90065

Application / Permit
19016-10000-01786
Plan Check / Job No.
B19LA01257
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE AND STORAGE INTO ACCESSORY DWELLING UNIT PER AB494 AND SB229. ADD CEILING BEAM PER ENGINEERING
Permit Issued
Issued on 2/19/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2019 APPLICANT
Assigned to Plan Check Engineer 1/22/2019 GEORGE ALVAREZ
Corrections Issued 1/22/2019 GEORGE ALVAREZ
Plan Check Approved 1/30/2020 KEVIN MORALES
Issued 2/19/2020 LADBS
CofO in Progress 10/26/2021 CRAIG VAUGHAN
CofO Issued 11/18/2021 DEROLD HAUFF
Permit Finaled 11/18/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/22/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 1/22/2019 JEANETTE VONG
Roof/Waste drainage to street Cleared 1/22/2019 JEANETTE VONG
Sewer availability Cleared 1/22/2019 JEANETTE VONG
Specific Plan Cleared 2/11/2019 JOHN DACEY
ZI Cleared 2/11/2019 JOHN DACEY
Construction near power lines Cleared 12/23/2019 RIDWAN HARDY
Permit Cleared 1/15/2020 ERIK BEASLEY
Trees in Parkway Cleared 1/29/2020 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/6/2020 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 7/14/2020 Conditional Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 7/17/2020 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/24/2020 Approved CRAIG VAUGHAN
Deputy Drilled-In Anchors 8/21/2020 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 8/24/2020 Partial Inspection CRAIG VAUGHAN
Underground Mechanical 8/28/2020 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 9/10/2020 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 9/30/2020 Approved CRAIG VAUGHAN
HVAC-Rough 9/30/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 9/30/2020 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 10/2/2020 Approved CRAIG VAUGHAN
Deputy Drilled-In Anchors 11/6/2020 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 11/10/2020 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 11/10/2020 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 11/10/2020 Approved CRAIG VAUGHAN
Insulation 11/10/2020 Approved CRAIG VAUGHAN
Drywall Nailing 11/25/2020 Approved CRAIG VAUGHAN
Drywall Nailing 11/30/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 12/2/2020 Partial Approval HAMIK HARTOUNIAN
HVAC-Final 3/17/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Final 3/17/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 3/30/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 4/9/2021 Approved CRAIG VAUGHAN
Final 5/4/2021 Corrections Issued CRAIG VAUGHAN
HVAC-Final 5/4/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/4/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 5/4/2021 Approved CRAIG VAUGHAN
Final 5/14/2021 Conditional Approval CRAIG VAUGHAN