14656 W SATICOY ST 91405

Certificate Information: 14656 W SATICOY ST 91405

Application / Permit
19016-10000-01488
Plan Check / Job No.
B19LA01070
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
VERIFY WORK DONE UNDER PERMIT NUMBER 14016 - 20000 - 11661 COMPLIES WITH SOFT STORY RETROFIT PER LABC CHAPTER 93. ADDITIONAL FOUNDATION WORK AND FRAMING WORK.
Permit Issued
Issued on 3/4/2020
Issuing Office
Metro
Current Status
CofC Issued on 8/31/2021

Permit Application Status History

Submitted 1/17/2019 APPLICANT
Assigned to Plan Check Engineer 2/7/2019 MANUEL MONTUFAR
Corrections Issued 2/11/2019 MANUEL MONTUFAR
Quality Review Completed 2/11/2019 HANS SANTIAGO
Building Plans Picked Up 2/13/2019 APPLICANT
Plan Check Approved 12/5/2019 MANUEL MONTUFAR
Issued 3/4/2020 LADBS
OK for CofC 6/8/2021 KENNETH ROBERTS
CofC Issued 8/31/2021 RICKEY JACKSON

Permit Application Clearance Information

Housing rent stabilization Cleared 2/19/2020 MICHAEL SOTO

Contact Information

Contractor Ace Construction Inc; Lic. No.: 809243-B 11921 SHERMAN WAY      NORTH HOLLYWOOD, CA 91605
Engineer Labib,, Youhanna T; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/15/2020 Not Ready for Inspection DANIEL VARNUM
Deputy Steel/Welding 3/3/2021 Conditional Approval BRUCE CAMPBELL
Deputy Steel/Welding 3/5/2021 Conditional Approval BRUCE CAMPBELL
Deputy Steel/Welding 3/15/2021 Conditional Approval BRUCE CAMPBELL
Footing/Foundation/Slab 3/19/2021 Approved DANIEL VARNUM
Structural Steel Frame 3/19/2021 Not Ready for Inspection DANIEL VARNUM
Wood Frame 3/19/2021 Not Ready for Inspection DANIEL VARNUM
Footing/Foundation/Slab 3/22/2021 Approved DANIEL VARNUM
Structural Steel Frame 3/22/2021 Approved DANIEL VARNUM
Wood Frame 3/22/2021 Approved DANIEL VARNUM
Interior/Exterior Lathing 4/28/2021 Approved DANIEL VARNUM
Final 5/14/2021 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 5/14/2021 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 5/14/2021 Not Ready for Inspection DANIEL VARNUM
Final 5/21/2021 Partial Approval DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 5/21/2021 SGSOV Approved DANIEL VARNUM
Smoke Detectors 5/21/2021 Approved DANIEL VARNUM
Final 6/8/2021 OK for CofC KENNETH ROBERTS