156 S HAYWORTH AVE 90048
Certificate Information: 156 S HAYWORTH AVE 90048
- Application / Permit
- 19016-10000-01451
- Plan Check / Job No.
- B19LA01032
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 3 STEEL SPECIAL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 3/15/2021
- Issuing Office
- Current Status
- CofC Issued on 7/21/2021
Permit Application Status History
| Submitted | 1/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2019 | CHUNG-WEN CHUANG |
| Corrections Issued | 2/19/2019 | CHUNG-WEN CHUANG |
| Quality Review Completed | 2/21/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 3/7/2019 | APPLICANT |
| Plan Check Approved | 3/28/2019 | CHUNG-WEN CHUANG |
| Issued | 3/15/2021 | APPLICANT |
| OK for CofC | 6/8/2021 | DARRYL ARNOLD |
| CofC Issued | 7/21/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 12/10/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Seismic Retrofit Solutions Inc; Lic. No.: 1023483-B | 16060 VENTURA BLVD STE 148 ENCINO, CA 91436 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/24/2021 | Corrections Issued | JONATHAN QUACH |
| Deputy Steel/Welding | 4/7/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 4/27/2021 | Conditional Approval | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 4/28/2021 | Approved | JONATHAN QUACH |
| Structural Steel Frame | 4/28/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 4/28/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Deputy Reinf. Concrete | 5/5/2021 | Conditional Approval | JONATHAN QUACH |
| Wood Frame | 5/10/2021 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 5/19/2021 | Approved | JONATHAN QUACH |
| Final | 6/4/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 6/4/2021 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 6/4/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 6/4/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 6/8/2021 | OK for CofC | DARRYL ARNOLD |
| Smoke Detectors | 6/8/2021 | Approved | DARRYL ARNOLD |