223 W 15TH ST 90731
Certificate Information: 223 W 15TH ST 90731
- Application / Permit
- 19016-10000-01447
- Plan Check / Job No.
- B19LA01031
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL (3) SPECAIL CANTILEVER COLUMN
- Permit Issued
- Issued on 2/21/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 3/23/2021
Permit Application Status History
| Submitted | 1/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2019 | VARAND SARKISIAN |
| Corrections Issued | 2/21/2019 | VARAND SARKISIAN |
| Quality Review Completed | 2/25/2019 | SAI KHUM |
| Building Plans Picked Up | 3/7/2019 | APPLICANT |
| Plan Check Approved | 4/16/2019 | VARAND SARKISIAN |
| Issued | 2/21/2020 | LADBS |
| OK for CofC | 3/22/2021 | MARK FERRARI |
| CofC Issued | 3/23/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/20/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Seismic Retrofit Solutions Inc; Lic. No.: 1023483-B | 18345 VENTURA BLVD STE 510 TARZANA, CA 91356 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/19/2020 | Corrections Issued | JOEY BUCHANAN |
| Footing/Foundation/Slab | 11/5/2020 | Corrections Issued | JOEY BUCHANAN |
| Structural Steel Frame | 11/5/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 11/5/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Footing/Foundation/Slab | 12/3/2020 | Approved | JOEY BUCHANAN |
| Structural Steel Frame | 12/3/2020 | Approved | JOEY BUCHANAN |
| Wood Frame | 12/3/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Structural Steel Frame | 12/23/2020 | Approved | NICK LAROCCA |
| Wood Frame | 12/23/2020 | Approved | NICK LAROCCA |
| Drywall Nailing | 1/21/2021 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 1/21/2021 | Approved | JOEY BUCHANAN |
| Final | 2/8/2021 | Corrections Issued | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 2/8/2021 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 2/8/2021 | Corrections Issued | MARK FERRARI |
| Final | 3/5/2021 | Corrections Issued | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 3/5/2021 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 3/5/2021 | Approved | MARK FERRARI |
| Final | 3/22/2021 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 3/22/2021 | SGSOV Approved | MARK FERRARI |