1418 E 110TH ST 90059
Certificate Information: 1418 E 110TH ST 90059
- Application / Permit
- 19016-10000-01436
- Plan Check / Job No.
- B19LA01023
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING 2- CAR DETACHED GARAGE TO UNPERMITTED DWELLING UNIT PER ADM-2018-3821-UDU
- Permit Issued
- Issued on 7/13/2022
- Issuing Office
- Current Status
- CofO Issued on 6/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2019 | PRANITA SHAH |
| Plans on Hold | 2/21/2019 | MINYE PAK |
| Green Plans Picked Up | 3/15/2019 | APPLICANT |
| Hold Released | 3/29/2019 | MINYE PAK |
| Corrections Issued | 3/29/2019 | PRANITA SHAH |
| Quality Review Completed | 4/18/2019 | MINYE PAK |
| Building Plans Picked Up | 4/19/2019 | APPLICANT |
| Applicant returned to address corrections | 7/17/2019 | PRANITA SHAH |
| Applicant returned to address corrections | 9/22/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 10/11/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 5/18/2021 | PRANITA SHAH |
| Plan Check Approved | 12/21/2021 | PRANITA SHAH |
| Issued | 7/13/2022 | APPLICANT |
| CofO in Progress | 6/21/2025 | DAVID FEILER |
| Permit Finaled | 6/23/2025 | RICHARD STEINBACH |
| CofO Issued | 6/23/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/23/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2019 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2019 | CELINA MORENO |
| Housing rent stabilization | Cleared | 4/19/2019 | STEVEN HOFSTAD |
| Sewer availability | Cleared | 4/19/2019 | CELINA MORENO |
| Density Bonus 14.00.A.10 | Cleared | 2/10/2020 | NICHOLAS KAWAZOE |
| Green Code | Cleared | 3/12/2020 | SARAH ABOULHOSN |
| ZI | Cleared | 5/20/2021 | HELEN JADALI |
| Unpermitted Dwelling Unit | Cleared | 10/25/2021 | MAIDEL LUEVANO |
Contact Information
| Contractor | La Rocca Builders Inc; Lic. No.: 934161-B | 14320 VENTURA BLVD STE 724 SHERMAN OAKS, CA 91423 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/26/2022 | Corrections Issued | JOHN KLARIN |
| Pre-Inspection | 9/7/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 10/17/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 10/17/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 10/17/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/17/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 10/31/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 10/31/2022 | Approved | JOHN KLARIN |
| Wood Frame | 10/31/2022 | Approved | JOHN KLARIN |
| Insulation | 11/3/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 11/3/2022 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/10/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 12/6/2022 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/23/2022 | Approved | JOHN KLARIN |
| Final | 12/23/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 12/23/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 12/23/2022 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/23/2022 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 12/23/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 2/7/2023 | Approved | JOHN KLARIN |
| Final | 2/7/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 2/7/2023 | Approved | JOHN KLARIN |
| HVAC-Final | 2/7/2023 | Approved | JOHN KLARIN |
| PLUMBING-Final | 2/7/2023 | Approved | JOHN KLARIN |
| Final | 2/28/2023 | Corrections Issued | JOHN KLARIN |
| Special/Order Compliance | 5/8/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 6/21/2025 | OK to Issue CofO | DAVID FEILER |