3061 W GLENHURST AVE 90039

Certificate Information: 3061 W GLENHURST AVE 90039

Application / Permit
19016-10000-00926
Plan Check / Job No.
B19LA00646
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED CONVERSION OF AN EXISTING PLAYROOM AND GARAGE INTO AN ACCESSORY DWELLING UNIT AB 494 and SB 229
Permit Issued
Issued on 9/3/2019
Issuing Office
Metro
Current Status
CofO Issued on 7/31/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2019 APPLICANT
Assigned to Plan Check Engineer 1/11/2019 ARSALAN SHABESTARI
Corrections Issued 1/11/2019 ARSALAN SHABESTARI
Applicant returned to address corrections 7/11/2019 SINA KHOSRAVI
Plan Check Approved 7/11/2019 SHANGQIN XIE
Issued 9/3/2019 LADBS
CofO in Progress 7/13/2020 ENRIQUE MIRELES
Permit Finaled 7/31/2020 DEROLD HAUFF
Permit Finaled 7/31/2020 DEROLD HAUFF
CofO Issued 7/31/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/28/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/28/2019 CELINA MORENO
Sewer availability Cleared 1/28/2019 CELINA MORENO
ZI Cleared 1/28/2019 LATANYA ROUX
Construction near power lines Cleared 7/11/2019 NADER ISKANDER
Construction within easement Cleared 7/11/2019 NADER ISKANDER

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 12/31/2019 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 12/31/2019 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/8/2020 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 1/8/2020 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/9/2020 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 1/9/2020 Approved HAMIK HARTOUNIAN
HVAC-Rough 1/9/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Shower Pan 1/9/2020 Approved HAMIK HARTOUNIAN
Smoke Detectors 1/9/2020 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/10/2020 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/27/2020 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/27/2020 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/27/2020 Approved HAMIK HARTOUNIAN
HVAC-Rough 4/27/2020 Approved HAMIK HARTOUNIAN
Insulation 4/27/2020 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/5/2020 Corrections Issued HAMIK HARTOUNIAN
Gas Test 5/5/2020 Corrections Issued HAMIK HARTOUNIAN
Insulation 5/5/2020 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/5/2020 Partial Approval HAMIK HARTOUNIAN
Sewer 5/5/2020 Corrections Issued HAMIK HARTOUNIAN
Drywall Nailing 5/12/2020 Approved HAMIK HARTOUNIAN
Insulation 5/12/2020 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/12/2020 Approved HAMIK HARTOUNIAN
Shower Pan 5/12/2020 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/20/2020 Approved HAMIK HARTOUNIAN
Gas Test 5/20/2020 Approved HAMIK HARTOUNIAN
Sewer 5/20/2020 Approved HAMIK HARTOUNIAN
Underground Mechanical 5/20/2020 Approved HAMIK HARTOUNIAN
Final 6/23/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 6/23/2020 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/23/2020 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 6/23/2020 Approved HAMIK HARTOUNIAN
Final 6/26/2020 Corrections Issued ENRIQUE MIRELES
Final 7/13/2020 OK to Issue CofO ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/13/2020 SGSOV Approved ENRIQUE MIRELES