1673 S MALCOLM AVE 90024
Certificate Information: 1673 S MALCOLM AVE 90024
- Application / Permit
- 19016-10000-00804
- Plan Check / Job No.
- B19LA00546
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93 USING STEEL CANTILEVER COLUMN
- Permit Issued
- Issued on 9/13/2021
- Issuing Office
- Current Status
- CofC Issued on 2/17/2022
Permit Application Status History
| Submitted | 1/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2019 | HANS SANTIAGO |
| Corrections Issued | 2/19/2019 | HANS SANTIAGO |
| Quality Review Completed | 2/21/2019 | SAI KHUM |
| Building Plans Picked Up | 2/28/2019 | APPLICANT |
| Plan Check Approved | 3/18/2019 | Andrew Santiago |
| Issued | 9/13/2021 | APPLICANT |
| OK for CofC | 2/7/2022 | PAUL DAVIDSON |
| CofC Issued | 2/17/2022 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 9/10/2021 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/20/2021 | Approved | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 9/28/2021 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 10/5/2021 | Approved | GRANT WOODS |
| Structural Steel Frame | 10/5/2021 | Approved | GRANT WOODS |
| Wood Frame | 10/5/2021 | Approved | GRANT WOODS |
| Deputy Reinf. Concrete | 10/7/2021 | Conditional Approval | GRANT WOODS |
| Interior/Exterior Lathing | 10/18/2021 | Approved | PAUL DAVIDSON |
| Final | 2/3/2022 | No Access for Inspection | PAUL DAVIDSON |
| METHANE-Final | 2/3/2022 | No Access for Inspection | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 2/3/2022 | SGSOV Not Ready | PAUL DAVIDSON |
| Smoke Detectors | 2/3/2022 | No Access for Inspection | PAUL DAVIDSON |
| Final | 2/7/2022 | OK for CofC | PAUL DAVIDSON |
| METHANE-Final | 2/7/2022 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 2/7/2022 | Approved | PAUL DAVIDSON |