1581 S MANNING AVE 90024
Certificate Information: 1581 S MANNING AVE 90024
- Application / Permit
- 19016-10000-00764
- Plan Check / Job No.
- B19LA00523
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL ONE (N) STEEL SPECIAL CANTILEVERED COLUMN.
- Permit Issued
- Issued on 5/14/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 10/23/2020
Permit Application Status History
| Submitted | 1/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2019 | TEODORO DIAZ RODRIGUEZ |
| Corrections Issued | 2/13/2019 | TEODORO DIAZ RODRIGUEZ |
| Quality Review Completed | 2/15/2019 | SAI KHUM |
| Building Plans Picked Up | 2/20/2019 | APPLICANT |
| Plan Check Approved | 4/5/2019 | TEODORO DIAZ RODRIGUEZ |
| Issued | 5/14/2020 | LADBS |
| OK for CofC | 8/18/2020 | PAUL DAVIDSON |
| CofC Issued | 10/23/2020 | TED RIES |
Permit Application Clearance Information
| "Q" conditions | Cleared | 4/2/2019 | ANNA VAN |
| Housing rent stabilization | Cleared | 2/13/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lara,, Arath Saude; Lic. No.: C68626 | 7778 VALLE VISTA DRIVE RANCHO CUCAMONGA, CA 91730 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/22/2020 | Approved | PAUL DAVIDSON |
| Deputy Steel/Welding | 6/2/2020 | Conditional Approval | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 6/16/2020 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 6/18/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 6/18/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Insulation | 6/18/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Smoke Detectors | 6/18/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Structural Steel Frame | 6/18/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Wood Frame | 6/18/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 6/19/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 6/19/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Insulation | 6/19/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Structural Steel Frame | 6/19/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Wood Frame | 6/19/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 7/6/2020 | Approved | PAUL DAVIDSON |
| Footing/Foundation/Slab | 7/6/2020 | Approved | PAUL DAVIDSON |
| Insulation | 7/6/2020 | Approved | PAUL DAVIDSON |
| Structural Steel Frame | 7/6/2020 | Approved | PAUL DAVIDSON |
| Wood Frame | 7/6/2020 | Approved | PAUL DAVIDSON |
| Interior/Exterior Lathing | 7/15/2020 | Conditional Approval | PAUL DAVIDSON |
| METHANE-Final | 7/20/2020 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 7/20/2020 | SGSOV Not Ready | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 7/24/2020 | SGSOV Not Ready | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 8/4/2020 | SGSOV Not Ready | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 8/6/2020 | SGSOV Not Ready | PAUL DAVIDSON |
| Final | 8/18/2020 | OK for CofC | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 8/18/2020 | SGSOV Approved | PAUL DAVIDSON |
| Smoke Detectors | 8/18/2020 | Approved | PAUL DAVIDSON |