1581 S MANNING AVE 90024

Certificate Information: 1581 S MANNING AVE 90024

Application / Permit
19016-10000-00764
Plan Check / Job No.
B19LA00523
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL ONE (N) STEEL SPECIAL CANTILEVERED COLUMN.
Permit Issued
Issued on 5/14/2020
Issuing Office
Metro
Current Status
CofC Issued on 10/23/2020

Permit Application Status History

Submitted 1/9/2019 APPLICANT
Assigned to Plan Check Engineer 2/7/2019 TEODORO DIAZ RODRIGUEZ
Corrections Issued 2/13/2019 TEODORO DIAZ RODRIGUEZ
Quality Review Completed 2/15/2019 SAI KHUM
Building Plans Picked Up 2/20/2019 APPLICANT
Plan Check Approved 4/5/2019 TEODORO DIAZ RODRIGUEZ
Issued 5/14/2020 LADBS
OK for CofC 8/18/2020 PAUL DAVIDSON
CofC Issued 10/23/2020 TED RIES

Permit Application Clearance Information

"Q" conditions Cleared 4/2/2019 ANNA VAN
Housing rent stabilization Cleared 2/13/2020 MICHAEL GREGERSON

Contact Information

Contractor Owner-Builder       ,
Engineer Lara,, Arath Saude; Lic. No.: C68626 7778 VALLE VISTA DRIVE      RANCHO CUCAMONGA, CA 91730

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/22/2020 Approved PAUL DAVIDSON
Deputy Steel/Welding 6/2/2020 Conditional Approval PAUL DAVIDSON
Deputy Drilled-In Anchors 6/16/2020 Conditional Approval PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 6/18/2020 Not Ready for Inspection PAUL DAVIDSON
Footing/Foundation/Slab 6/18/2020 Not Ready for Inspection PAUL DAVIDSON
Insulation 6/18/2020 Not Ready for Inspection PAUL DAVIDSON
Smoke Detectors 6/18/2020 Not Ready for Inspection PAUL DAVIDSON
Structural Steel Frame 6/18/2020 Not Ready for Inspection PAUL DAVIDSON
Wood Frame 6/18/2020 Not Ready for Inspection PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 6/19/2020 Not Ready for Inspection PAUL DAVIDSON
Footing/Foundation/Slab 6/19/2020 Not Ready for Inspection PAUL DAVIDSON
Insulation 6/19/2020 Not Ready for Inspection PAUL DAVIDSON
Structural Steel Frame 6/19/2020 Not Ready for Inspection PAUL DAVIDSON
Wood Frame 6/19/2020 Not Ready for Inspection PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 7/6/2020 Approved PAUL DAVIDSON
Footing/Foundation/Slab 7/6/2020 Approved PAUL DAVIDSON
Insulation 7/6/2020 Approved PAUL DAVIDSON
Structural Steel Frame 7/6/2020 Approved PAUL DAVIDSON
Wood Frame 7/6/2020 Approved PAUL DAVIDSON
Interior/Exterior Lathing 7/15/2020 Conditional Approval PAUL DAVIDSON
METHANE-Final 7/20/2020 Approved PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 7/20/2020 SGSOV Not Ready PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 7/24/2020 SGSOV Not Ready PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 8/4/2020 SGSOV Not Ready PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 8/6/2020 SGSOV Not Ready PAUL DAVIDSON
Final 8/18/2020 OK for CofC PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 8/18/2020 SGSOV Approved PAUL DAVIDSON
Smoke Detectors 8/18/2020 Approved PAUL DAVIDSON