631 W 10TH ST 90731
Certificate Information: 631 W 10TH ST 90731
- Application / Permit
- 19016-10000-00747
- Plan Check / Job No.
- B19LA00507
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft story retrofit per LAMC Div 93: (1) Ordinary Moment Frame
- Permit Issued
- Issued on 8/11/2020
- Issuing Office
- Current Status
- CofC Issued on 12/22/2020
Permit Application Status History
| Submitted | 1/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2019 | HERNAN ARREOLA |
| Corrections Issued | 2/11/2019 | HERNAN ARREOLA |
| Quality Review Completed | 2/12/2019 | SAI KHUM |
| Building Plans Picked Up | 3/4/2019 | APPLICANT |
| Plan Check Approved | 3/22/2019 | HERNAN ARREOLA |
| Issued | 8/11/2020 | APPLICANT |
| OK for CofC | 12/21/2020 | JOEY BUCHANAN |
| CofC Issued | 12/22/2020 | NICK LAROCCA |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 3/13/2019 | JIM URQUHART |
| Housing rent stabilization | Cleared | 8/7/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/24/2020 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 9/21/2020 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 9/23/2020 | Approved | JOEY BUCHANAN |
| Structural Steel Frame | 9/23/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 9/23/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 9/28/2020 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 10/9/2020 | Approved | JOEY BUCHANAN |
| Final | 12/4/2020 | Corrections Issued | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 12/4/2020 | SGSOV Not Ready | JOEY BUCHANAN |
| Smoke Detectors | 12/4/2020 | Approved | JOEY BUCHANAN |
| Final | 12/21/2020 | OK for CofC | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 12/21/2020 | SGSOV Approved | JOEY BUCHANAN |