631 W 10TH ST 90731

Certificate Information: 631 W 10TH ST 90731

Application / Permit
19016-10000-00747
Plan Check / Job No.
B19LA00507
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft story retrofit per LAMC Div 93: (1) Ordinary Moment Frame
Permit Issued
Issued on 8/11/2020
Issuing Office
Current Status
CofC Issued on 12/22/2020

Permit Application Status History

Submitted 1/9/2019 APPLICANT
Assigned to Plan Check Engineer 2/7/2019 HERNAN ARREOLA
Corrections Issued 2/11/2019 HERNAN ARREOLA
Quality Review Completed 2/12/2019 SAI KHUM
Building Plans Picked Up 3/4/2019 APPLICANT
Plan Check Approved 3/22/2019 HERNAN ARREOLA
Issued 8/11/2020 APPLICANT
OK for CofC 12/21/2020 JOEY BUCHANAN
CofC Issued 12/22/2020 NICK LAROCCA

Permit Application Clearance Information

Project located in CRA area Cleared 3/13/2019 JIM URQUHART
Housing rent stabilization Cleared 8/7/2020 STEVEN HOFSTAD

Contact Information

Contractor Optimum Seismic Inc; Lic. No.: 1012702-B 5508 S SANTA FE AVENUE      VERNON, CA 90058
Engineer Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 1377 S BEVERLY GLEN BLVD 308      LOS ANGELES, CA 90024

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/24/2020 Approved JOEY BUCHANAN
Deputy Drilled-In Anchors 9/21/2020 Approved JOEY BUCHANAN
Footing/Foundation/Slab 9/23/2020 Approved JOEY BUCHANAN
Structural Steel Frame 9/23/2020 Not Ready for Inspection JOEY BUCHANAN
Wood Frame 9/23/2020 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 9/28/2020 Approved JOEY BUCHANAN
Interior/Exterior Lathing 10/9/2020 Approved JOEY BUCHANAN
Final 12/4/2020 Corrections Issued JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 12/4/2020 SGSOV Not Ready JOEY BUCHANAN
Smoke Detectors 12/4/2020 Approved JOEY BUCHANAN
Final 12/21/2020 OK for CofC JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 12/21/2020 SGSOV Approved JOEY BUCHANAN