6227 N CRANER AVE 91606
Certificate Information: 6227 N CRANER AVE 91606
- Application / Permit
- 19016-10000-00612
- Plan Check / Job No.
- B19LA00410
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft Story Retrofit as per LABC Ch. 93. Install 1 (N) OMF.
- Permit Issued
- Issued on 8/11/2020
- Issuing Office
- Current Status
- CofC Issued on 5/5/2021
Permit Application Status History
| Submitted | 1/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2019 | JAIME OROZCO |
| Corrections Issued | 2/5/2019 | JAIME OROZCO |
| Quality Review Completed | 2/5/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 2/8/2019 | APPLICANT |
| Plan Check Approved | 5/21/2019 | JAIME OROZCO |
| Issued | 8/11/2020 | APPLICANT |
| OK for CofC | 4/19/2021 | KENNETH ROBERTS |
| CofC Issued | 5/5/2021 | RICKEY JACKSON |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 6/9/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Biayna Corp; Lic. No.: 998853-B | 9751 WHEATLAND AVE SUNLAND, CA 91040 |
| Engineer | Muradyan,, David; Lic. No.: S6232 | 10233 JOHANNA AVE SUNLAND, CA 91040 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/18/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 9/10/2020 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 9/10/2020 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 9/10/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/10/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 9/16/2020 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 12/10/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 12/10/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 12/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 12/17/2020 | Approved | JOE VELASQUEZ |
| Insulation | 12/23/2020 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 12/23/2020 | Conditional Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 1/13/2021 | Approved | JOE VELASQUEZ |
| Final | 2/24/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/24/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 2/24/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 4/19/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 4/19/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 4/19/2021 | Approved | KENNETH ROBERTS |