344 S MANHATTAN PL 90020
Certificate Information: 344 S MANHATTAN PL 90020
- Application / Permit
- 19016-10000-00007
- Plan Check / Job No.
- B18LA27940
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY SEISMIC RETROFIT PER LAMC CHAPTER 93: INSTALL STEEL MOMENT FRAMES
- Permit Issued
- Issued on 2/5/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 2/8/2021
Permit Application Status History
| Submitted | 1/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2019 | MANUEL MONTUFAR |
| Corrections Issued | 1/23/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 1/30/2019 | HANS SANTIAGO |
| Plan Check Approved | 6/14/2019 | MANUEL MONTUFAR |
| Issued | 2/5/2020 | LADBS |
| OK for CofC | 9/15/2020 | DARRYL ARNOLD |
| CofC Issued | 2/8/2021 | DAVID TSAU |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 6/13/2019 | JIM URQUHART |
| Housing rent stabilization | Cleared | 1/29/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Cal Retrofit; Lic. No.: 1022167-B | 6900 CANBY AVE #108 RESEDA, CA 91335 |
| Engineer | Jones,, Richard Alan; Lic. No.: S4977 | 5058 VIA INGRESSO YORBA LINDA, CA 92886 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/27/2020 | Approved | BRUCE CAMPBELL |
| Pre-Inspection | 3/4/2020 | Corrections Issued | BRUCE CAMPBELL |
| Deputy Steel/Welding | 4/23/2020 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 6/8/2020 | Partial Approval | FELIX CEBALLOS |
| Deputy Reinf. Concrete | 6/8/2020 | Partial Approval | FELIX CEBALLOS |
| Footing/Foundation/Slab | 6/12/2020 | Corrections Issued | FELIX CEBALLOS |
| Deputy Steel/Welding | 6/19/2020 | Conditional Approval | FRED WOHLFARTH |
| Footing/Foundation/Slab | 6/22/2020 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 6/24/2020 | Conditional Approval | FRED WOHLFARTH |
| Deputy Steel/Welding | 6/26/2020 | Conditional Approval | FRED WOHLFARTH |
| Deputy Steel/Welding | 6/29/2020 | Conditional Approval | FRED WOHLFARTH |
| Deputy Steel/Welding | 6/30/2020 | Conditional Approval | FRED WOHLFARTH |
| Deputy Steel/Welding | 7/1/2020 | Conditional Approval | JONATHAN QUACH |
| Structural Steel Frame | 7/23/2020 | Approved | MARK FERRARI |
| Wood Frame | 7/23/2020 | Approved | MARK FERRARI |
| Deputy Steel/Welding | 7/24/2020 | Conditional Approval | FRED WOHLFARTH |
| Interior/Exterior Lathing | 8/18/2020 | Corrections Issued | VAHE KELEDJIAN |
| Final | 9/15/2020 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 9/15/2020 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 9/15/2020 | Approved | DARRYL ARNOLD |