6057 W 82ND ST 90045

Certificate Information: 6057 W 82ND ST 90045

Application / Permit
19014-70000-06973
Plan Check / Job No.
B19SL01823
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
775 SF (25.5' x 22.5' ) ADDITION TO GARAGE TO INCLUDE FRONT PORCH (25' x 9') AND 373 SF (18' x 20.5') GARAGE CONVERSION TO ATTACHED ADU TO BE TOTAL RFA 2836 SF PER AB 494 AND SB 229
Permit Issued
Issued on 5/20/2020
Issuing Office
Current Status
CofO Issued on 7/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Assigned to Plan Check Engineer 1/10/2020 STARR CHEN
Corrections Issued 1/14/2020 STARR CHEN
Quality Review Completed 1/14/2020 JASON HEALEY
Building Plans Picked Up 1/23/2020 APPLICANT
Green Plans Picked Up 2/4/2020 APPLICANT
Plan Check Approved 3/17/2020 STARR CHEN
Issued 5/20/2020 APPLICANT
CofO in Progress 9/30/2021 BRENDAN LOONEY
No Progress 4/4/2022 RICHARD STEINBACH
CofO in Progress 7/14/2022 RICHARD STEINBACH
Permit Finaled 7/14/2022 KENNETH NAGLE
CofO Issued 7/14/2022 KENNETH NAGLE
Permit Finaled 7/14/2022 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 2/14/2020 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 2/14/2020 JAMES MORALEZ
Sewer availability Cleared 2/14/2020 JAMES MORALEZ
Construction near power lines Cleared 3/6/2020 RIDWAN HARDY
Construction within easement Cleared 3/6/2020 RIDWAN HARDY
Green Code Cleared 3/11/2020 STARR CHEN
Low Impact Development Cleared 3/17/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 3/17/2020 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/29/2020 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 7/7/2020 Approved JUAN VALENZUELA
Footing/Foundation/Slab 7/7/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 7/22/2020 Partial Approval CRAIG DAVIS
Green Building Rough 7/22/2020 Not Ready for Inspection CRAIG DAVIS
Deputy Wood Construction 7/23/2020 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 9/29/2020 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 9/29/2020 Approved JOHNNY MIRANDA
Gas Test 9/29/2020 Approved JOHNNY MIRANDA
Green Building Rough 9/29/2020 Approved JOHNNY MIRANDA
HVAC-Rough 9/29/2020 Corrections Issued JOHNNY MIRANDA
Interior/Exterior Lathing 9/29/2020 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 9/29/2020 Corrections Issued JOHNNY MIRANDA
Sewer 9/29/2020 Approved JOHNNY MIRANDA
HVAC-Rough 10/5/2020 Approved JUAN VALENZUELA
Insulation 10/5/2020 Approved JUAN VALENZUELA
PLUMBING-Rough 10/5/2020 Approved JUAN VALENZUELA
Drywall Nailing 10/13/2020 Approved JUAN VALENZUELA
Shower Pan 12/4/2020 Approved DAVID HEINE
Interior/Exterior Lathing 12/16/2020 Corrections Issued JOHNNY MIRANDA
Interior/Exterior Lathing 12/17/2020 Approved JOHNNY MIRANDA
Final 5/6/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 5/6/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 5/6/2021 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 5/6/2021 Approved BRENDAN LOONEY
Final 6/25/2021 Corrections Issued BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 6/25/2021 SGSOV Not Ready BRENDAN LOONEY
Final 7/13/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 7/13/2021 SGSOV Not Ready BRENDAN LOONEY
Verify Rec and Parks Fee Memo 7/13/2021 Approved BRENDAN LOONEY
Final 9/29/2021 OK to Issue CofO BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 9/29/2021 SGSOV Approved BRENDAN LOONEY