6057 W 82ND ST 90045
Certificate Information: 6057 W 82ND ST 90045
- Application / Permit
- 19014-70000-06973
- Plan Check / Job No.
- B19SL01823
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 775 SF (25.5' x 22.5' ) ADDITION TO GARAGE TO INCLUDE FRONT PORCH (25' x 9') AND 373 SF (18' x 20.5') GARAGE CONVERSION TO ATTACHED ADU TO BE TOTAL RFA 2836 SF PER AB 494 AND SB 229
- Permit Issued
- Issued on 5/20/2020
- Issuing Office
- Current Status
- CofO Issued on 7/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2020 | STARR CHEN |
| Corrections Issued | 1/14/2020 | STARR CHEN |
| Quality Review Completed | 1/14/2020 | JASON HEALEY |
| Building Plans Picked Up | 1/23/2020 | APPLICANT |
| Green Plans Picked Up | 2/4/2020 | APPLICANT |
| Plan Check Approved | 3/17/2020 | STARR CHEN |
| Issued | 5/20/2020 | APPLICANT |
| CofO in Progress | 9/30/2021 | BRENDAN LOONEY |
| No Progress | 4/4/2022 | RICHARD STEINBACH |
| CofO in Progress | 7/14/2022 | RICHARD STEINBACH |
| Permit Finaled | 7/14/2022 | KENNETH NAGLE |
| CofO Issued | 7/14/2022 | KENNETH NAGLE |
| Permit Finaled | 7/14/2022 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 2/14/2020 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2020 | JAMES MORALEZ |
| Sewer availability | Cleared | 2/14/2020 | JAMES MORALEZ |
| Construction near power lines | Cleared | 3/6/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/6/2020 | RIDWAN HARDY |
| Green Code | Cleared | 3/11/2020 | STARR CHEN |
| Low Impact Development | Cleared | 3/17/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/17/2020 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/29/2020 | Partial Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 7/7/2020 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/7/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 7/22/2020 | Partial Approval | CRAIG DAVIS |
| Green Building Rough | 7/22/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Deputy Wood Construction | 7/23/2020 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/29/2020 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/29/2020 | Approved | JOHNNY MIRANDA |
| Gas Test | 9/29/2020 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 9/29/2020 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 9/29/2020 | Corrections Issued | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/29/2020 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 9/29/2020 | Corrections Issued | JOHNNY MIRANDA |
| Sewer | 9/29/2020 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 10/5/2020 | Approved | JUAN VALENZUELA |
| Insulation | 10/5/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 10/5/2020 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 10/13/2020 | Approved | JUAN VALENZUELA |
| Shower Pan | 12/4/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 12/16/2020 | Corrections Issued | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 12/17/2020 | Approved | JOHNNY MIRANDA |
| Final | 5/6/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 5/6/2021 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 5/6/2021 | SGSOV Not Ready | BRENDAN LOONEY |
| Smoke Detectors | 5/6/2021 | Approved | BRENDAN LOONEY |
| Final | 6/25/2021 | Corrections Issued | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Not Ready | BRENDAN LOONEY |
| Final | 7/13/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 7/13/2021 | SGSOV Not Ready | BRENDAN LOONEY |
| Verify Rec and Parks Fee Memo | 7/13/2021 | Approved | BRENDAN LOONEY |
| Final | 9/29/2021 | OK to Issue CofO | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 9/29/2021 | SGSOV Approved | BRENDAN LOONEY |