5855 N BURNET AVE 91411
Certificate Information: 5855 N BURNET AVE 91411
- Application / Permit
- 19014-70000-06676
- Plan Check / Job No.
- B19SL01734
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One Story addition to existing single family dwelling & interior remodel
- Permit Issued
- Issued on 12/18/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Corrected on 11/14/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2019 | PRANITA SHAH |
| Corrections Issued | 12/9/2019 | PRANITA SHAH |
| Plan Check Approved | 12/18/2019 | RICARDO RAMIREZ |
| Issued | 12/18/2019 | LADBS |
| CofO in Progress | 8/26/2020 | WILLIAM KUEHN |
| CofO Issued-Status Void | 10/31/2020 | MICHAEL SMITH |
| Permit Finaled-Status Void | 10/31/2020 | MICHAEL SMITH |
| Re-Activate Permit | 11/2/2020 | MICHAEL SMITH |
| No Progress | 11/2/2020 | MICHAEL SMITH |
| CofO in Progress | 11/14/2020 | MICHAEL SMITH |
| CofO Corrected | 11/14/2020 | MICHAEL SMITH |
| Permit Finaled | 11/14/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2019 | THOMAS LANG |
| Hold | Cleared | 12/18/2019 | CYNTHIA RYAN |
| Roof/Waste drainage to street | Cleared | 12/18/2019 | THOMAS LANG |
| Sewer availability | Cleared | 12/18/2019 | THOMAS LANG |
| ZI | Cleared | 12/18/2019 | ANNA VAN |
Contact Information
| Contractor | Precision Construction Experts Inc; Lic. No.: 1026997-B | 16656 CALLE ARBOLADA PACIFIC PALISADES, CA 90272 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/31/2019 | Conditional Approval | ARAM AVEDISIAN |
| Wood Frame | 1/3/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Insulation | 1/7/2020 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 1/7/2020 | Corrections Issued | MARK JOHNSON |
| BUILDING-Rough-Frame | 1/8/2020 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 1/8/2020 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/8/2020 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/14/2020 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 1/14/2020 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 1/14/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 1/14/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/14/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Shower Pan | 1/14/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/17/2020 | No Access for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 1/17/2020 | No Access for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/17/2020 | No Access for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2020 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/22/2020 | Approved | ARAM AVEDISIAN |
| Shower Pan | 1/22/2020 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/24/2020 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 1/24/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/24/2020 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 1/28/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/28/2020 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 2/20/2020 | Approved | MISAEL ESPARZA |
| Insulation | 2/20/2020 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 6/4/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 6/4/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/4/2020 | Approved | MISAEL ESPARZA |
| Gas Test | 6/4/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 6/4/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 6/4/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 6/4/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 6/4/2020 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 6/4/2020 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/5/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Final | 8/5/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Green Building Final | 8/5/2020 | No Access for Inspection | WILLIAM KUEHN |
| HVAC-Final | 8/5/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| PLUMBING-Final | 8/5/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 8/5/2020 | SGSOV Not Ready | WILLIAM KUEHN |
| Service/Power Release | 8/5/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Final | 8/25/2020 | OK to Issue CofO | WILLIAM KUEHN |
| Green Building Final | 8/25/2020 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2020 | SGSOV Approved | WILLIAM KUEHN |