2353 W FAIR PARK AVE 90041

Certificate Information: 2353 W FAIR PARK AVE 90041

Application / Permit
19014-70000-06456
Plan Check / Job No.
B19SL01673
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO SINGLE FAMILY DWELLING AND REMODEL.
Permit Issued
Issued on 1/24/2020
Issuing Office
Metro
Current Status
CofO Issued on 8/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 TEODORO DIAZ RODRIGUEZ
Corrections Issued 11/26/2019 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 12/6/2019 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 1/22/2020 RICARDO RAMIREZ
Issued 1/24/2020 LADBS
CofO in Progress 8/4/2020 CRAIG VAUGHAN
CofO in Progress 8/17/2020 CRAIG VAUGHAN
Permit Finaled 8/21/2020 DEROLD HAUFF
Permit Finaled 8/21/2020 DEROLD HAUFF
CofO Issued 8/21/2020 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/3/2019 PATRICK MISCHLICH
Eng Process Fee Ord 176,300 Cleared 12/6/2019 THOMAS LANG
Hydrant and Access approval Cleared 12/6/2019 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 12/6/2019 THOMAS LANG

Contact Information

Contractor J N N General Contractors Inc; Lic. No.: 1019980-B 2915 STOCKBRIDGE AVENUE      LOS ANGELES, CA 90032
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/28/2020 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 1/30/2020 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 2/3/2020 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 2/7/2020 Partial Approval CRAIG VAUGHAN
Green Building Rough 2/7/2020 Not Ready for Inspection CRAIG VAUGHAN
METHANE-Rough 2/7/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 2/7/2020 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 2/12/2020 Partial Approval COREY HUPP
BUILDING-Rough-Frame 3/6/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 3/6/2020 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Partial Approval CRAIG VAUGHAN
Green Building Rough 3/6/2020 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 3/6/2020 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 3/6/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 3/6/2020 Not Ready for Inspection CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 3/6/2020 Not Ready for Inspection CRAIG VAUGHAN
Shower Pan 3/6/2020 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/11/2020 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 3/12/2020 No Access for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/20/2020 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 4/6/2020 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 4/6/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 4/6/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 4/6/2020 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 4/9/2020 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 4/9/2020 Approved CRAIG VAUGHAN
Green Building Rough 4/9/2020 Partial Approval CRAIG VAUGHAN
HVAC-Rough 4/9/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 4/9/2020 Approved CRAIG VAUGHAN
Shower Pan 4/9/2020 Approved CRAIG VAUGHAN
Green Building Rough 4/14/2020 Approved CRAIG VAUGHAN
Insulation 4/14/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 4/14/2020 Partial Approval CRAIG VAUGHAN
Drywall Nailing 4/20/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/20/2020 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/30/2020 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 5/20/2020 Partial Approval CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/22/2020 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 7/14/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Final 7/14/2020 Corrections Issued CRAIG VAUGHAN
Final 7/14/2020 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 7/14/2020 Approved CRAIG VAUGHAN
Gas Test 7/14/2020 Corrections Issued CRAIG VAUGHAN
Green Building Final 7/14/2020 Approved CRAIG VAUGHAN
HVAC-Final 7/14/2020 Corrections Issued CRAIG VAUGHAN
METHANE-Barrier 7/14/2020 Approved CRAIG VAUGHAN
METHANE-Subgrade 7/14/2020 Approved CRAIG VAUGHAN
PLUMBING-Final 7/14/2020 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/14/2020 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 7/14/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Final 7/22/2020 Approved CRAIG VAUGHAN
Final 7/22/2020 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 7/22/2020 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 7/22/2020 Corrections Issued CRAIG VAUGHAN
Service/Power Release 7/22/2020 Approved CRAIG VAUGHAN
Final 7/29/2020 Conditional Approval CRAIG VAUGHAN
Final 8/14/2020 OK to Issue CofO CRAIG VAUGHAN