5928 E WEAVER ST 90042
Certificate Information: 5928 E WEAVER ST 90042
- Application / Permit
- 19014-70000-06094
- Plan Check / Job No.
- B19SL01568
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- TWO STORY ADDITION TO (E) ONE STORY SINGLE FAMILY DWELLING. TYPE VB FULLY SPRINKLERED.
- Permit Issued
- Issued on 3/11/2021
- Issuing Office
- Current Status
- CofO Issued on 6/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | RICARDO RAMIREZ |
| Corrections Issued | 11/27/2019 | RICARDO RAMIREZ |
| Quality Review Completed | 12/3/2019 | TEODORO DIAZ RODRIGUEZ |
| Green Plans Picked Up | 12/17/2019 | APPLICANT |
| Applicant returned to address corrections | 10/14/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 11/24/2020 | RICARDO RAMIREZ |
| Plan Check Approved | 3/11/2021 | RICARDO RAMIREZ |
| Issued | 3/11/2021 | APPLICANT |
| Building Plans Picked Up | 3/12/2021 | APPLICANT |
| CofO in Progress | 6/22/2022 | CRAIG VAUGHAN |
| Permit Finaled | 6/28/2022 | DEROLD HAUFF |
| CofO Issued | 6/28/2022 | DEROLD HAUFF |
| Permit Finaled | 6/28/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/19/2020 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 8/19/2020 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 8/19/2020 | WALLIE JONG |
| Sewer availability | Cleared | 8/19/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2020 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 1/28/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 2/4/2021 | MARTIN FRAGOSO |
| Grading Pre-Inspection | Cleared | 2/16/2021 | RICARDO RAMIREZ |
| Green Code | Cleared | 2/16/2021 | NEGAR NEJAD |
| Roof/Waste drainage to street | Cleared | 3/10/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrizosa,, Richard Garcia; Lic. No.: C86224 | 1505 LYNDHURST AVE HACIENDA HEIGHTS, CA 917452932 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/21/2021 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/3/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/19/2021 | Partial Approval | COREY HUPP |
| Green Building Rough | 5/19/2021 | Not Ready for Inspection | COREY HUPP |
| Verify Sprinkler Sign Off | 5/19/2021 | Not Ready for Inspection | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2021 | Partial Approval | COREY HUPP |
| HVAC-Rough | 9/23/2021 | Partial Inspection | COREY HUPP |
| PLUMBING-Rough | 9/23/2021 | Partial Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 10/13/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/13/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 10/13/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 10/13/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/13/2021 | Partial Approval | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 10/13/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/4/2021 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/4/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 11/4/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/4/2021 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 11/4/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/8/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 11/8/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/8/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/10/2021 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 11/10/2021 | Approved | CRAIG VAUGHAN |
| Deputy Wood Construction | 11/16/2021 | No Access for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/19/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 12/2/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 12/2/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 12/23/2021 | Approved | AMY COLIN |
| Final | 3/23/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 3/23/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 3/23/2022 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 3/23/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 3/23/2022 | Approved | CRAIG VAUGHAN |
| Final | 6/13/2022 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Final | 6/21/2022 | Approved | CRAIG VAUGHAN |
| Final | 6/21/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 6/21/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 6/21/2022 | Approved | CRAIG VAUGHAN |