6631-6633 N BOTHWELL ROAD 91335
Certificate Information: 6631-6633 N BOTHWELL ROAD 91335
- Application / Permit
- 19014-70000-06012
- Plan Check / Job No.
- B19SL01544
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION TO (E) SINGLE FAMILY DWELLING FOR MASTER BEDROOM AND REMODEL EXTEND (E) GARAGE TO CONVERT TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 7/17/2020
- Issuing Office
- Current Status
- CofO Issued on 7/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2019 | JESSE ARELLANO |
| Corrections Issued | 12/13/2019 | JESSE ARELLANO |
| Quality Review Completed | 12/17/2019 | BILL STUTSMAN |
| Green Plans Picked Up | 12/23/2019 | APPLICANT |
| Building Plans Picked Up | 1/9/2020 | APPLICANT |
| Plan Check Approved | 7/17/2020 | JESSE ARELLANO |
| Issued | 7/17/2020 | APPLICANT |
| CofO in Progress | 5/5/2022 | VINCENT HANLEY |
| Permit Finaled | 7/21/2022 | MICHAEL SMITH |
| CofO Issued | 7/21/2022 | MICHAEL SMITH |
| Permit Finaled | 7/21/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/9/2020 | TORI CHEN |
| Hydrant and Access approval | Cleared | 1/9/2020 | JEREMY CARTER |
| Sewer availability | Cleared | 1/9/2020 | CELINA MORENO |
| Address approval | Cleared | 1/10/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2020 | ERIK BEASLEY |
| Green Code | Cleared | 1/30/2020 | VIVIAN LAO |
| Low Impact Development | Cleared | 2/21/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 3/19/2020 | EMIL KYUPELYAN |
| Trees in Parkway | Cleared | 3/19/2020 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 9/8/2020 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 9/22/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 9/22/2020 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2021 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 1/26/2021 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/25/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 3/25/2021 | Approved | VINCENT HANLEY |
| Gas Test | 3/25/2021 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 3/25/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 3/25/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 3/25/2021 | Approved | VINCENT HANLEY |
| Sewer | 3/25/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 4/13/2021 | Approved | VINCENT HANLEY |
| Insulation | 4/13/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/13/2021 | Approved | VINCENT HANLEY |
| Shower Pan | 4/13/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/10/2021 | Corrections Issued | VINCENT HANLEY |
| Final | 6/10/2021 | Corrections Issued | VINCENT HANLEY |
| Gas Test | 6/10/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 6/10/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 6/10/2021 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 6/10/2021 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/10/2021 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 6/10/2021 | Corrections Issued | VINCENT HANLEY |
| Smoke Detectors | 6/10/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/5/2022 | Approved | VINCENT HANLEY |
| Final | 5/5/2022 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 5/5/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/5/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/5/2022 | SGSOV Approved | VINCENT HANLEY |