847 E 91ST ST 90002
Certificate Information: 847 E 91ST ST 90002
- Application / Permit
- 19014-70000-05921
- Plan Check / Job No.
- B19SL01519
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT AND ADDITION (E) TEMP DWELLING INTO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 11/10/2020
- Issuing Office
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | CARLOS MONTES |
| Corrections Issued | 12/3/2019 | EVERARDO SANTOS |
| Quality Review Completed | 12/3/2019 | LAWRENCE QUIRANTE |
| Green Plans Picked Up | 12/5/2019 | APPLICANT |
| Building Plans Picked Up | 12/6/2019 | APPLICANT |
| Applicant returned to address corrections | 9/23/2020 | CARLOS MONTES |
| Plan Check Approved | 11/4/2020 | CARLOS MONTES |
| Issued | 11/10/2020 | APPLICANT |
| CofO in Progress | 9/3/2021 | EUGENE CASSIDY |
| No Progress | 9/18/2021 | ANSON MAGLASANG |
| CofO in Progress | 1/21/2022 | ANSON MAGLASANG |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
| CofO Issued | 1/22/2022 | DEROLD HAUFF |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/17/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 12/17/2019 | EMIL KYUPELYAN |
| Community Plan Implem. Overlay | Cleared | 1/6/2020 | HELEN JADALI |
| Green Code | Cleared | 1/17/2020 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 7/22/2020 | ROBIN YAMADA |
| Community Plan Implem. Overlay | Cleared | 9/16/2020 | DALE WILLIAMS |
| Roof/Waste drainage to street | Cleared | 10/2/2020 | ROSA SILVA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/18/2020 | Corrections Issued | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 11/23/2020 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 11/25/2020 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 11/25/2020 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 12/14/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 12/14/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/17/2020 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 12/17/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 12/17/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 12/23/2020 | Not Ready for Inspection | COREY HUPP |
| Interior/Exterior Lathing | 12/23/2020 | Not Ready for Inspection | COREY HUPP |
| Wood Frame | 12/23/2020 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 12/29/2020 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 12/29/2020 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 12/29/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Wood Frame | 12/29/2020 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 12/31/2020 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 1/5/2021 | Conditional Approval | JOSEPH MCGARRY |
| Drywall Nailing | 1/5/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 2/4/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/4/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 2/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/4/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 2/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/4/2021 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/4/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/9/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/14/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/14/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/14/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/14/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/14/2021 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/14/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/24/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/24/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/2/2021 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 9/2/2021 | Approved | EUGENE CASSIDY |