13312 W HERRON ST 91342

Certificate Information: 13312 W HERRON ST 91342

Application / Permit
19014-70000-05906
Plan Check / Job No.
B19SL01512
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 STORY ADDITION AT THE REAR TO AN (E) SFD WITH ATTACHED GARAGE. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 11/7/2019
Issuing Office
Metro
Current Status
CofO Issued on 2/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2019 APPLICANT
Assigned to Plan Check Engineer 10/30/2019 LUKE GONZALES
Corrections Issued 10/30/2019 LUKE GONZALES
Plan Check Approved 11/7/2019 KEVIN MORALES
Issued 11/7/2019 LADBS
CofO in Progress 2/15/2023 DAVID ANDERSON
Permit Finaled 2/15/2023 MICHAEL SMITH
CofO Issued 2/15/2023 MICHAEL SMITH
Permit Finaled 2/15/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/1/2019 JAMES MORALEZ
Roof/Waste drainage to street Cleared 11/1/2019 JAMES MORALEZ
Sewer availability Cleared 11/1/2019 JAMES MORALEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/29/2019 Partial Approval CHARLES POWELL
Deputy Drilled-In Anchors 12/2/2019 Approved CHARLES POWELL
BUILDING-Rough-Frame 12/27/2019 Corrections Issued CHARLES POWELL
Green Building Rough 12/27/2019 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 12/27/2019 Not Ready for Inspection CHARLES POWELL
Footing/Foundation/Slab 2/18/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 2/28/2020 Corrections Issued JOHN HAYES
Green Building Rough 2/28/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 2/28/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 3/6/2020 Partial Approval JENNIFER RABUCHIN
Green Building Rough 3/6/2020 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 3/6/2020 Partial Approval JENNIFER RABUCHIN
Insulation 3/11/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 9/29/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 9/29/2020 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/29/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 9/29/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 9/29/2020 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/26/2020 Partial Approval MISAEL ESPARZA
Wood Frame 10/26/2020 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 12/7/2020 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 12/7/2020 Corrections Issued MISAEL ESPARZA
Green Building Final 12/7/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 12/7/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 12/7/2020 Approved MISAEL ESPARZA
Smoke Detectors 12/7/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 12/9/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 6/9/2021 Approved KRISTEN CAUSEY
Insulation 6/17/2021 Partial Approval DEANDRE HOFFMAN
Drywall Nailing 1/31/2022 No Access for Inspection KRISTEN CAUSEY
Insulation 1/31/2022 No Access for Inspection KRISTEN CAUSEY
Drywall Nailing 2/4/2022 Approved JOHN HAYES
Insulation 2/4/2022 Approved JOHN HAYES
Shower Pan 6/9/2022 Approved JOHN HAYES
Interior/Exterior Lathing 7/11/2022 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 2/14/2023 Approved DAVID ANDERSON
Final 2/14/2023 OK to Issue CofO DAVID ANDERSON
Green Building Final 2/14/2023 Approved DAVID ANDERSON
Green Building Rough 2/14/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 2/14/2023 SGSOV Approved DAVID ANDERSON
Service/Power Release 2/14/2023 Approved DAVID ANDERSON
Smoke Detectors 2/14/2023 Approved DAVID ANDERSON