2843 1/2 S HOLT AVE 90034

Certificate Information: 2843 1/2 S HOLT AVE 90034

Application / Permit
19014-70000-05815
Plan Check / Job No.
B19SL01480
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. INSTALL AUTOMATIC FIRE SPRINKLERS.
Permit Issued
Issued on 3/2/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/27/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 ALBERT SERVIN
Corrections Issued 11/7/2019 ALBERT SERVIN
Green Plans Picked Up 11/7/2019 APPLICANT
Quality Review Completed 11/14/2019 KEN GILL
Building Plans Picked Up 11/21/2019 APPLICANT
Applicant returned to address corrections 1/29/2020 ALBERT SERVIN
Plan Check Approved 2/7/2020 ALBERT SERVIN
Plan Check Approved 2/12/2020 ALBERT SERVIN
Issued 3/2/2020 LADBS
CofO in Progress 10/26/2020 KENNETH NAGLE
CofO Issued 10/27/2020 VINCENT COTTON
Permit Finaled 10/27/2020 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 11/7/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 11/7/2019 THOMAS LANG
Sewer availability Cleared 11/7/2019 THOMAS LANG
Street width determination Cleared 11/7/2019 THOMAS LANG
Green Code Cleared 11/26/2019 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/22/2020 Partial Approval DANNY TOLENTINO
Deputy Wood Construction 6/23/2020 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 7/6/2020 Partial Approval EVAN COOPER
Green Building Rough 7/6/2020 Not Ready for Inspection EVAN COOPER
MERV13>=Rough 7/6/2020 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 7/21/2020 Approved JUSTIN CURTIS
Floor/Roof Diaphrgm/Shear Wall 7/21/2020 Approved JUSTIN CURTIS
Gas Test 7/21/2020 Approved JUSTIN CURTIS
Green Building Rough 7/21/2020 Not Ready for Inspection JUSTIN CURTIS
MERV13>=Rough 7/21/2020 Not Ready for Inspection JUSTIN CURTIS
PLUMBING-Rough 7/21/2020 Approved JUSTIN CURTIS
Rough-Elec/Plmb/HVAC 7/21/2020 Approved JUSTIN CURTIS
Sewer 7/21/2020 Approved JUSTIN CURTIS
BUILDING-Rough-Frame 7/24/2020 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 7/29/2020 Approved EVAN COOPER
Green Building Rough 7/29/2020 Approved EVAN COOPER
Insulation 7/29/2020 Partial Approval EVAN COOPER
Interior/Exterior Lathing 7/29/2020 Approved EVAN COOPER
MERV13>=Rough 7/29/2020 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/5/2020 Approved EVAN COOPER
Insulation 8/5/2020 Approved EVAN COOPER
Drywall Nailing 8/11/2020 Approved EVAN COOPER
ELECTRICAL-Final 8/28/2020 Not Ready for Inspection EVAN COOPER
Service/Power Release 8/28/2020 Approved EVAN COOPER
ELECTRICAL-Final 9/29/2020 Approved EVAN COOPER
Final 9/29/2020 Corrections Issued EVAN COOPER
Green Building Final 9/29/2020 Approved EVAN COOPER
HVAC-Final 9/29/2020 Approved EVAN COOPER
MERV13>=Final 9/29/2020 Approved EVAN COOPER
PLUMBING-Final 9/29/2020 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/29/2020 SGSOV Approved EVAN COOPER
Smoke Detectors 9/29/2020 Approved EVAN COOPER
Final 10/2/2020 Conditional Approval EVAN COOPER