8715 S GLIDER AVE 90045
Certificate Information: 8715 S GLIDER AVE 90045
- Application / Permit
- 19014-70000-05627
- Plan Check / Job No.
- B19SL01424
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 7/14/2020
- Issuing Office
- Current Status
- CofO Issued on 10/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | RICARDO RAMIREZ |
| Corrections Issued | 10/31/2019 | RICARDO RAMIREZ |
| Quality Review Completed | 10/31/2019 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 11/12/2019 | APPLICANT |
| Green Plans Picked Up | 5/20/2020 | APPLICANT |
| Applicant returned to address corrections | 6/15/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 6/23/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 6/29/2020 | RICARDO RAMIREZ |
| Plan Check Approved | 6/30/2020 | RICARDO RAMIREZ |
| Plan Check Approved | 6/30/2020 | LISA THAMIZ |
| Issued | 7/14/2020 | APPLICANT |
| CofO in Progress | 10/7/2024 | BOBBY KEY |
| Permit Finaled | 10/15/2024 | RICHARD STEINBACH |
| CofO Issued | 10/15/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/15/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2020 | JEANIE LAM |
| Low Impact Development | Cleared | 2/10/2020 | MARTIN FRAGOSO |
| Permit | Cleared | 2/10/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 2/10/2020 | JEANIE LAM |
| Sewer availability | Cleared | 2/10/2020 | JEANIE LAM |
| Green Code | Cleared | 5/20/2020 | VIVIAN LAO |
Contact Information
| Contractor | Torres Ricardo Enriquez; Lic. No.: 1044900-B | 1530 E 88TH STREET LOS ANGELES, CA 90002 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/7/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 6/7/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 7/7/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 7/26/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 8/18/2023 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 8/18/2023 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 11/1/2023 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 12/6/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 12/6/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 12/6/2023 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 12/26/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 12/26/2023 | Approved | BOBBY KEY |
| Green Building Rough | 12/26/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 12/26/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/26/2023 | Partial Approval | BOBBY KEY |
| Insulation | 12/28/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 1/5/2024 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 1/5/2024 | Approved | RICHARD STEINBACH |
| ELECTRICAL-Final | 2/13/2024 | Corrections Issued | BOBBY KEY |
| Final | 2/13/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 2/13/2024 | Approved | BOBBY KEY |
| HVAC-Final | 2/13/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 2/13/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 2/13/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 2/13/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 10/7/2024 | Approved | BOBBY KEY |
| Final | 10/7/2024 | OK to Issue CofO | BOBBY KEY |