1735 1/2 W 59TH ST 90047
Certificate Information: 1735 1/2 W 59TH ST 90047
- Application / Permit
- 19014-70000-05496
- Plan Check / Job No.
- B19SL01380
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL. WILL ADD 2 NEW BEDROOMS AND WILL RELOCATE KITCHEN.
- Permit Issued
- Issued on 12/11/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2019 | TEODORO DIAZ RODRIGUEZ |
| Corrections Issued | 10/8/2019 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 11/22/2019 | LUKE GONZALES |
| Issued | 12/11/2019 | LADBS |
| CofO in Progress | 8/30/2023 | ENRIQUE MIRELES |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| CofO Issued | 9/5/2023 | DEROLD HAUFF |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2019 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 11/14/2019 | EMIL KYUPELYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/23/2020 | Corrections Issued | HORACE FULTZ |
| Wood Frame | 3/25/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 4/1/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 4/1/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Wood Frame | 4/1/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/7/2020 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/7/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/7/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 4/7/2020 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 4/8/2020 | No Access for Inspection | FREDDIE RIVERA |
| Wood Frame | 4/8/2020 | No Access for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/15/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/15/2020 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 4/15/2020 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 4/24/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/24/2020 | Partial Approval | SABAS ALONSO |
| Special/Order Compliance | 4/29/2020 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 5/13/2020 | Approved | SABAS ALONSO |
| Final | 8/25/2020 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 8/25/2020 | Approved | FREDDIE RIVERA |
| Green Building Final | 8/25/2020 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/25/2020 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 8/25/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 8/31/2020 | OK to Issue CofO | FREDDIE RIVERA |
| Gas Test | 8/31/2020 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/31/2020 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 8/31/2020 | Approved | FREDDIE RIVERA |